Job Recruitment Website - Property management - What is the technical disclosure of fire fighting construction?
What is the technical disclosure of fire fighting construction?
1 The fire protection design drawings of building projects must be construction drawings designed by design units with corresponding design qualification certificates and approved by fire control institutions.
2 The construction must be carried out in strict accordance with the approved fire protection design drawings, so as to achieve "construction according to the drawings" and shall not be changed without authorization.
3 The installed fire protection products, mechanical and electrical products and materials shall meet the following conditions:
3. 1 There are two types of equipment and materials used in fire protection engineering: special fire protection products and non-special general products.
Fire protection products: such as sprinkler heads, water flow indicators, fire pumps, alarm valve groups, water pump adapters, etc. of automatic sprinkler systems;
General products: such as galvanized steel pipes, pressure stabilizing pumps, pressure gauges, pressure reducing valves, check valves, gate valves, etc.
3.2 The purchased fire protection products shall have the compulsory product certification certificate or product type approval certificate issued by the fire protection product conformity assessment center of the Ministry of Public Security, and the certificate shall be within the validity period.
3.3 The purchased general-purpose products shall have a type test report, which shall be within the effective inspection period after passing the inspection.
3.4 The selected high and low voltage cabinets, various box screens, wires and cables shall have certificates of conformity and 3C certificates, and the equipment shall have nameplates.
3.5 All kinds of steel selected shall meet the relevant standards and design requirements, and the manufacturer shall issue the material certificate and certificate of conformity.
3.6 All kinds of main fittings, pipe fittings, covered electrode, paints, etc. Should have a certificate.
4 The selected machines and tools must meet the technical requirements of the construction site, and the measuring instruments with or without compulsory inspection shall be managed according to the requirements of the national metrology law.
5 construction management personnel, such as the builder, quality inspector, material engineer, etc. , should hold relevant certificates. Special types of work, such as electricians and welders, should also hold relevant certificates.
During the construction of the project, it shall be inspected and guided by superior units such as public security fire control institutions and quality supervision organs to ensure the quality of the project.
7 Carry out the construction in strict accordance with the approved design drawings, and seriously implement the construction requirements such as fire protection design specifications, construction acceptance specifications, construction technology, relevant atlas and manufacturer's information.
8 The collection, sorting and archiving of construction project records and data should be synchronized with the project, and a full set of engineering data should be handed over to the construction unit when the project is completed and accepted, and the as-built drawings should be drawn according to the contract requirements.
9 After the installation and commissioning of the fire protection project is completed, the construction unit shall conduct self-inspection first, and then report it to the construction unit (supervision unit) for completion acceptance, and handle the completion acceptance sheet.
10 cooperate with the construction unit or the building fire control facilities inspection unit entrusted by the construction unit to conduct technical inspection and actively rectify the problems.
1 1 Cooperate with the construction unit to submit an acceptance application to the public security fire control institution, send relevant materials, participate in the acceptance of fire control projects hosted by the public security fire control institution, actively rectify the problems raised in the acceptance process, and handle the project handover formalities in time after passing the acceptance.
- Previous article:How long did Mengyin County sentence Gong Yanlong to?
- Next article:Deferred property fee accounting subjects
- Related articles
- How about the decoration of Pingdingshan Jinding Building?
- What is the telephone number of the marketing center of Kang Shu University in Fuzhou?
- How far is it from Xizhuang Village to Kunming Station?
- How to write the self-appraisal of the security officer who has become a full member?
- Do you know the telephone number of the property and check the owner's number?
- Profit of electric bicycle charging pile
- A security guard in Zhejiang was injured in the fire fighting. Why are tenants cut off from water and electricity?
- Is the transportation convenient in Jindi Tianhe Mansion? How should I get there?
- How long is the property right of Suizhou Park 1978?
- What about Guangdong Guo Hong Property Management Service Co., Ltd.?