Job Recruitment Website - Property management - What's the charge for installing a new electricity meter?

What's the charge for installing a new electricity meter?

Costs vary from place to place, such as:

Reply on relevant expense standards such as installation and renovation of electric energy meter

Jia [2004] No.88

Wuhu Power Supply Company:

Your Bureau's Report on Asking for Adjustment of Electric Energy Meter Installation and Renovation Charges (Wugong Marketing [2004] No.8) and Report on Asking for Reservation of Original Electric Power Management Project Charges and Approval of New Charges (Wugong Marketing [2004] No.23) have been received. In order to continue to accelerate the pace of urban residents' electricity consumption with one household and one meter, effectively improve the residents' electricity consumption conditions, and meet the new capacity needs of some residents and the actual needs of other power supply users, according to the spirit of the provincial price bureau's notice on strengthening the service price management of urban water supply, power supply and gas supply industries [200 1] 18 1 and other documents, combined with the actual situation of our city, through research,

A, watt-hour meter installation and renovation and other related expenses standards are still in accordance with the provisions of the Municipal Price Bureau (2002) 153 document, including:

(1) renovation fee standard of "one meter per household" for residents' electricity consumption in old residential buildings: "one meter per household" is implemented for electric energy meters (4kw), and the installation and renovation fee standard for the first and second floors is 470 yuan for each household, and 30 yuan will be added for each floor from the third floor (including the third floor).

(2) Old residential electricity users directly apply for the "one household, one meter" renovation of the 8kw watt-hour meter. The cost standard for the installation and renovation of the first and second floors is 695 yuan per household, and the 30 yuan is increased for each floor from the third floor (including the third floor).

(3) Residents who implement the principle of "one meter per household" and originally requested to change (5-20a) meters below 4kw will be charged for meter change, and each household will be in 20 yuan; It is required to change the original 4kw watt-hour meter to 8kw, and the renovation cost standard is 235 yuan per household; If the original watt-hour meter is less than 4kw, it needs to be changed to 8kw, and the renovation cost standard is 255 yuan per household.

Second, the charging standards for various electricity services carried out by power supply enterprises continue to be implemented according to the provisions of the Municipal Price Bureau 152 (see the attached table for details). Power supply enterprises shall adhere to the principle of user's voluntariness in carrying out various electricity services, and prohibit compulsory sales of goods and compulsory service charges during the service process, and shall not charge fees if they do not carry out services.

Three, according to the provisions of the State Planning Commission No.25 "Interim Measures for the Supervision and Examination of the Price and Cost of Important Commodities and Services", the above-mentioned electricity service charges are subject to annual examination. Please go to the window of the municipal administrative service center as soon as possible to go through the formalities for changing the business license and show the charging voucher. In the future, if there are new regulations in the country or province, they shall be implemented according to the new regulations.

June 24(th), 2004

Wuhu Power Supply Company Power Business Fee Collection Standard

serial number

kind

project

unit

Unit (yuan)

explain

1

Printing material fee

power supply contract

set up

6.00

A set of four books

2

Power transmission loss

Stop at the first branch

Dongsi

50.00

Including power loss, automobile shifting and labor cost; 1. A branch of a multi-family contract shall be regarded as a general branch. 2. If the suburban counties entrust rural fulgurite stations to operate, no operating fee will be charged.

Public distribution transformer and main branch stop power transmission.

Dongsi

100.00

The public trunk line is out of service (power outage charge 150 yuan)

Dongsi

300.00

three

Temporary electricity consumption without electricity meter

Permanent resident

Dongsi

10.00

Other users

Dongsi

30.00

four

Error of electric energy meter

Investigation fee

Single-phase 2.0 test

only

20.00

1, users must voluntarily apply for electric energy meter inspection; 2, watt-hour meter inspection qualified inspection fee receivable; 3. If the watt-hour meter inspection is really unqualified, the inspection fee for the watt-hour meter shall not be charged, and the overcharged fee shall be refunded to the user.

Level 2.0 Inspection Three-phase Four-wire Inspection

only

30.00

Three-phase four-wire 1.0 liquid level detection

only

40.00

Three-phase four-wire 0.5-level inspection

only

60.00

five

Pre-test cost of equipment

electric cable

root

100.00

Including insulation, withstand voltage, DC and grounding group tests.

Autumn insurance

group

50.00

Oil switch on column

platform

100.00

high-tension switch

platform

100.00

High voltage switchgear

platform

120.00

Transformers below 500 volts 10 volts and above

only

10.00-50.00

Lightning arrester 10KV

group

120.00

According to the power engineering quota.

Lightning arrester 35K

group

360.00

Capacitor 10KV

group

20.00

35KV capacitor

group

50.00

Safety equipment 10KV

individual

5.00

35KV safety equipment

individual

10.00

Nuclear phase 10KV

time

60.00

Nuclear phase 35KV

time

120.00

Bus withstand voltage

time

30.00

10KV interval pretest

time

60.00

35KV interval pretest

time

120.00

10KV switch

platform

60.00

10KV pole switch

platform

400.00

10KV insulator withstand voltage

only

2.00

35KV insulator withstand voltage

only

5.00

Partial discharge test

time

200.00

Insulation Resistance Test (Centralized)

time

40.00

Insulation resistance test (grounding grid)

time

200.00

six

Transformer power

Test cost

10KV, 3 15KV and below.

taiji

360.00

According to the power engineering quota.

800KVA

taiji

450.00

1600KVA

taiji

600.00

2000 kva

taiji

900.00

35KV, 400KVA and below

taiji

450.00

1000KVA

taiji

600.00

2500 kva

taiji

900.00

10000KVA

taiji

1200.00

seven

Compensation for electric energy meter

single - phase kilowatt - hour meter

only

70.00

Users who damage the electric energy meter should pay compensation according to the original price.

Single-phase electronic energy meter

only

68.00

Single-phase anti-theft electronic watch

only

129.00

Three-phase four-wire electronic watch

only

460.00

Three-phase three-wire, three-phase four-wire complex rate electronic meter

only

720.00

Three-phase three-wire (grade 1.0s) and three-phase four-wire multifunctional electronic watches.

only

720.00

Three-phase three-wire (0.5s class) multifunctional electronic watch

only

2700.00

Three-phase four-wire prepaid watt-hour meter

only

980.00

Pressure loss, cut-off and short-circuit timer

only

2500.00