Measures for comprehensive acceptance of the completion of urban residential quarters in Fuzhou City
The completion comprehensive acceptance team consists of the following units: the Municipal Construction Committee, the Municipal Appearance Management Committee, the Municipal Real Estate Management Bureau, the Municipal Urban and Rural Planning Bureau, the Municipal Environmental Protection Bureau, the Municipal Bureau of Gardens, the Municipal Electric Power Bureau, the Municipal Fire Brigade and other relevant departments involved in living conditions, as well as entrusted property management companies, district governments and streets. Members participating in the inspection team are fully entrusted by the above-mentioned units to perform the ultimate duties of various functional departments. Fifth residential development and construction units must organize development and construction according to the approved detailed planning requirements, and bear the final project quality responsibility for residential new village construction projects. The quality responsibility relationship between development and construction units and design and construction units shall be implemented in accordance with the provisions of relevant laws and regulations. Sixth residential areas with actual construction land of 0.5 hectares (including 0.5 hectares) or more shall be included in the scope of comprehensive acceptance of completion. 65438+65438 10 0997+ 1 By the date of promulgation of these Measures, the residential quarters that are still under construction or not should also be comprehensively accepted for completion.
Residential areas built by stages can apply for acceptance by stages according to the actual situation, but the acceptance area should be separated from the area under construction by walls, and the acceptance area should have living conditions. Article 7 Acceptance criteria:
1. All construction projects are completed according to the approved detailed construction planning and related professional management and design requirements, and meet the use requirements;
2 residential and public facilities, municipal public infrastructure, environmental protection facilities, link facilities and other single projects are qualified, and the acceptance information is complete;
3. All construction machines and tools, temporary facilities, building residual soil and remaining components shall be removed, and the site shall be cleared and leveled;
4. The plane position, facade modeling and decorative colors of all kinds of buildings meet the requirements of the approved detailed planning for construction;
5. The property management plan has been implemented;
6. The equipment has been running normally (such as elevators, pumps, etc.). ), and have the operation certificate issued by the relevant departments. Article 8 After the comprehensive acceptance is completed, the development and construction unit shall provide the following original materials:
1. Construction land planning permit, construction project planning permit, approved construction detailed planning and engineering design drawings (plane, elevation and profile) of each unit, etc. ;
2. The project completion acceptance certificate of each unit approved by the project quality supervision institution;
3. Completion documents and construction enterprise materials;
4 new village completion site plan, pipeline location site plan and underground pipeline comprehensive plan;
5. Other documents and information. Article 9 Comprehensive acceptance contents:
1. Whether the detailed planning requirements for construction have been fully implemented;
2. Check the quality acceptance sheet of each single project;
3. Infrastructure and public service facilities are completed;
4 demolition compensation and resettlement plan is implemented;
5. Whether the contents of the original approval of the construction project have changed, and whether the relevant procedures have been completed;
6 the implementation of the property management plan and whether the basic funds for property management are in place;
7. Implementation of sanitation facilities;
8. others. Article 10 Acceptance procedures:
1. Before formally handling the comprehensive acceptance of completion, the development and construction unit shall organize a pre-inspection team, focusing on checking the project quality, acceptance data of concealed works, construction records of key parts, notice of design change, construction according to drawings, and presence of omissions, etc.
2. The development and construction unit shall, after the completion of the pre-acceptance of residential areas, submit a written application for the comprehensive acceptance report to the Municipal Construction Committee, fill out the Declaration Form for the Comprehensive Acceptance of Residential Areas in quadruplicate and provide a written report on the results of the pre-acceptance, and also explain the organization and implementation of the development and construction projects and the results of the pre-acceptance;
3. After receiving the application report and declaration form for comprehensive acceptance, the Municipal Construction Committee will organize an acceptance team composed of relevant departments to conduct comprehensive acceptance of residential quarters within fifteen working days;
4. The members of the acceptance team shall be unified to the location of the acceptance project according to the specified time, presided over by the Municipal Construction Committee, focusing on reviewing relevant documents and materials, and after listening to the report of the construction unit, they shall go to the site for inspection;
5. The members of the acceptance team conduct on-site evaluation according to relevant information and on-site evaluation, and fill in the acceptance opinions in combination with their respective business scope;
6. The Municipal Construction Committee is responsible for summarizing the acceptance opinions of various functional departments and formally forming an acceptance summary;
7. The members of the inspection team signed the inspection opinions and sealed the inspection declaration form on the spot on behalf of the functional departments sent by them.
- Related articles
- Wang Yongping's resume
- What should I do if the wire in the community is broken? Who is in charge?
- Is the South Island Style Commercial Street in Fenghuang, Jiujiang District near the waterfront Chen Xing community?
- China Southwest Architectural Design and Research Institute qualification certificate.
- How about Marriott real estate?
- Where is Huizhou Zhongtian Rainbow City located and what are its advantages?
- What time does Hebi Xinxing Hanlin Mansion open?
- What is the telephone number of Baoding Baisheng Dongliwu Sales Department?
- Responsibilities of department personnel
- Where is the East Road of Xipeng Aluminium City Avenue?