What is the secondary decoration standard for shopping malls?

Application and approval process for secondary decoration of shopping malls:

(1) statement: the merchant/decoration contractor must provide the decoration plan in triplicate, and the area ratio is 1:50 or1:100 in metric system;

1, building plan, structure diagram and detailed description

2, the ceiling plan

3, electrical design drawings

4. Logo and light box design

5. Other related plans

At the same time, the decoration application form and the construction personnel pass application form must be filled in in detail.

Sign the decoration commitment letter and fire prevention agreement when decorating.

If hot work is required, a temporary hot work application form shall be filled in.

Fill in the Decoration Project Entry Application Form before the materials enter the site.

(2) Payment: The merchant/decoration contractor shall pay the decoration deposit, the construction personnel pass deposit (50 yuan/Taiwan) and the production fee (10 yuan/Taiwan) to the Finance Department under the guidance of the Property Department on the day of application.

(3) Examination and approval: The Property Department shall examine and guide the application materials and fill in the decoration application examination and approval form.

The approval time is generally five working days.

Others: If the scale of decoration works falls within the supervision scope of the fire department, the merchant shall apply to the fire department for construction, and the construction can only be started after being reviewed by the fire department.

(4) Certification: The Property Department issues the decoration permit to the approved merchants/decoration contractors, and the construction personnel pass to the decoration contractors.

(5) Construction supervision: The property management department supervises the decoration of all shops, and requires the decoration contractor to rectify immediately if there is any violation. If the circumstances are serious or disobey the management, it can stop work immediately.

(6) Completion Acceptance: After completion, the merchant/decoration contractor submits an acceptance application to the property department and fills in the Application Form for Completion Acceptance of Decoration Project.

The property management department generally completes the relevant acceptance work within five working days, fills in the acceptance registration form of the decoration project, and issues the opinions on the completion acceptance of the decoration project.

(7) Refund: The merchant/decoration contractor shall go to the Finance Department to handle the refund formalities with the Notice of Winning Bid for Decoration Project Completion and the relevant deposit receipt.

(8) Exit: When the decoration contractor leaves, it is required to issue the goods release form to the property department and consciously accept the inspection by the manager.