Job Recruitment Website - Property management - What are the main items and proportions of automatic fire alarm and fire linkage control equipment testing?
What are the main items and proportions of automatic fire alarm and fire linkage control equipment testing?
Time: June 6, 2003 18: 00: 42
Author:
First of all, explain:
1. The project is divided into three systems:
(1) Automatic fire alarm system (one person from each construction and commissioning unit shall cooperate with the detection).
(2) Automatic water supply system, fire hydrant system and automatic sprinkler system (the construction unit shall send one person to cooperate with the inspection).
③ Smoke control and extraction system (including ventilation, air conditioning, emergency lighting, evacuation instructions and fire separation)
2. The detection is divided into three stages:
① The first stage: single detection
② The second stage: chain detection.
③ The third stage: comprehensive re-examination.
3. During the whole testing work, the entrusting unit shall designate one person as the contact person and coordinator.
Second, the content:
Automatic fire alarm system:
The first stage:
① System wiring and fire control room detection
(2) Detect the fire detector, manual alarm button and fire display panel one by one.
③ Functional detection of fire alarm controller and fire linkage control equipment.
The second stage:
① Fire accident broadcasting, fire communication, acousto-optic alarm and remote on-off detection of fire elevator.
② Carry out overall linkage detection according to the designed linkage logic relationship.
The third stage: Re-examine the recommended rectification items in the above two stages one by one.
Fire water supply system:
The first stage:
① Detection of water pump house, outdoor fire fighting pipe network, indoor fire fighting pipe network and ancillary equipment.
(2) The drainage test of the drainage device at the end of each floor, the alarm detection of the water flow indicator and the function detection of the wet alarm valve.
(3) Fire hydrant buttons shall be tested for alarm function, dynamic pressure and static pressure one by one.
Phase II: ① Linkage test of fire hydrant pump and spray pump.
The third stage: Re-examine the items recommended for rectification in the above two stages.
Smoke control system:
The first stage:
(1) Manually test the fire valve, air supply valve and smoke exhaust valve one by one.
(2) Positive pressure blower, smoke exhaust fan and fire shutter door shall be detected on site.
(3) Detection of emergency lighting, evacuation lights and fire separation facilities.
The second stage:
(1) air conditioning new fan or non-fire power cut-off test.
② Remote opening and closing, fire damper, air supply valve, smoke exhaust valve, smoke exhaust fan and positive pressure fan.
③ Linkage detection of fire shutter doors
The third stage: Re-examine the items recommended for rectification in the above two stages.
- Related articles
- What about Xiamen Shapo Fishing Port Property Management Company?
- What are the reasons for informed criticism Zhengyi Property and informed criticism?
- Look at my birthday: Gregorian calendar 1985 was born on 13 at 5: 25 am on May 5, and it rained.
- Qingming greeting
- What is the telephone number of the sales office of Weibang Century Home in Wulanchabu?
- How about the property in the north area of Suyuan New Village?
- What are the main shortcomings of Hongyuan Xinyu four villages? Is it difficult to park?
- & gt& gt& gt hotline
- How to open a certificate of no income?
- What about Wuhan Hi-tech State Holding Group Co., Ltd.?