Project site construction sequence?

1. mat

Familiar with the construction drawing → Look at the planning red line → Check the leveling point → Tower crane foundation construction (set the water collecting ditch) → Measure the original landform elevation → Protect the positioning pile → Install the tower crane (apply for installation) → Release the excavation line → Technical disclosure → Mechanical excavation → Pay-off → Manual excavation leveling → Measure the elevation of the pile head and mark it → Break the pile head → Check the size and strain → Check the geosyncline → Pay-off → Woodworking formwork → Cushion.

Bedding should pay attention to the following issues:

1. Before bedding, control the height, elevation and plane size of the formwork. The soil should not be over-excavated or under-excavated.

2, cushion concrete shipped to the scene or in the process of processing to spot check the slump of cushion concrete, the same as the mixture ratio list.

3. Leave the concrete test block, the mix proportion list of cushion concrete, and the second interview report on the inspection of stones and sand, etc.

4, concrete in construction, to observe the smoothness of the concrete surface, can't call the construction unit darby leveling.

5, when pouring concrete, to consider the standby power supply, standby vibrator and other tools.

6, pouring concrete, supervision generally to stand by.

2. Foundation

Positioning and setting-out of foundation column → technical disclosure → carpentry shuttering → binding of bearing platform reinforcement → positioning of bearing platform reinforcement by electric welding → positioning of column reinforcement → embedding of water and electricity → foundation concrete → formwork removal → cleaning → foundation acceptance → earthwork backfilling.

3. Outside the frame erection

Technical disclosure → hardening of outer frame → drainage ditch → collecting ditch → erection of outer frame → hard sealing → hanging safety net → acceptance of outer frame.

4. subjects

Positioning and setting-out of main column → technical disclosure → column rebar binding → copying horizontal line (1m relation line) → water and electricity embedding → carpentry shuttering → plate rebar binding → water and electricity embedding → inspection (vertical, geometric dimensions and nodes) → concrete pouring → maintenance → formwork removal → cleaning → masonry 1m rice noodle → concrete strength detection.

5. Masonry building

Setting-out of masonry → technical disclosure → rebar planting → rebar planting pull-out detection → windowsill formwork support → windowsill concrete → laying bottom brick → precast concrete lintel and concrete block → laying aerated block → placing Rachel rebar → checking flatness → windowsill capping formwork support → removing windowsill capping formwork → laying precast concrete block → placing 1 m building concrete lintel →

6. Plaster (paint)

Technical disclosure → hanging steel wire mesh on the external wall → wetting water → throwing slurry → pasting ash cake → protecting corner → handing over the hole → installing doors and windows → wetting water → plastering rough surface ash → plastering ash → curing → pasting brick → jointing → cleaning → gluing doors and windows → installing glass → putty once → putty twice → polishing → primer → topcoat once → topcoat twice → sporadic sealing →

7. Removal of external frame

Notice of regular meeting → technical disclosure → Rachel's internal pulling → Rachel's drilling → Rachel's oxygen cutting → Fine stone concrete repair → Brick patching and paint patching → Safety net removal → Facade inspection → External wall acceptance → Outer frame removal → cleaning.

8. fence

Technical disclosure → structural embedment → erection and installation → pendant installation → wooden handrail installation → wooden handrail painting → cleaning.

9.the roof

Technical disclosure → water and electricity installation → hanging holes → manual cleaning →R angle → structural water stop → grass-roots handover → waterproof construction → waterproof water stop → waterproof handover → mortar leveling → insulation board → installation →PVC vent pipe → embedded parts → 4 @ 200× 200 steel mesh → joint width 10 @ 6000× 6000.

10. Floor

Technical disclosure → water and electricity suppression → ground mechanical cleaning → wet water → ash cake → slurry sweeping → pouring → maintenance → cleaning → ground installation.

1 1. wall brick

Technical disclosure → water and electricity suppression → typesetting → road finding → paving → cleaning → jointing → cleaning → kitchen and bathroom ceiling → sanitary ware installation → cabinet installation → hardware installation.

12. Floor tiles

Technical disclosure → water and electricity suppression → water and electricity installation → hanging holes → marble sill stone installation → manual cleaning →R angle (with waterproof requirements) → structural water stop → grass-roots handover → waterproof construction → waterproof handover → typesetting → finding a way → paving → cleaning → jointing → cleaning.

13. Indoor

Technical disclosure → drilling → nailing cork → installing bottom frame → installing door cover → installing surface → installing door leaf → installing door lock → cleaning.

14. ceiling

Technical disclosure → water and electricity suppression → elastic line → drawing keel step line → installing main keel suspender → installing main keel → installing secondary keel → concealed acceptance → installing gypsum board → painting antirust paint → installing layering → cleaning.

15. Dismantle the passenger and cargo elevator

Demolition → Close the passenger and cargo elevator (for demolition)

16. entrance door

Technical disclosure → drilling → nailing screws → installing door frames → installing door leaves → installing door locks → cleaning.

17. Hydropower generation

Technical disclosure → Foundation embedment → Main body embedment → Masonry slotting → Installation of junction boxes, conduits and water pipes → Grooving → Pressing → Installation of risers → Hanging holes → Indoor threading → Installation of lamps and lanterns → Electrical testing.

18. Property acceptance

Sub-item acceptance → ceramic tile → paint → floor → suspended ceiling → plastic steel doors and windows → interior door → entrance door → cabinet → railing → marble → special acceptance → suppression → ball passing → water collection → water spraying → electricity inspection.

19. Architecture

Pipe network construction → garden construction

20. Acceptance before delivery

Filing → pre-acceptance → rectification → site opening → rectification → acceptance → key collection.