Job Recruitment Website - Property management company - Fine decoration progress, you deserve it.
Fine decoration progress, you deserve it.
Step 1: Check the balance of water meter and electric meter on the first day of construction; Handle property management procedures (prepare property decoration deposit, management fee, customs clearance of goods). You'd better say hello in advance. What's the total cost? It is recommended to pack it yourself. A copy of the business license and qualification of the decoration company shall be stamped with a red seal; On-site disclosure: mainly including waterways, lines and lamps. If it is an old house, it will be opened after it is demolished; The concealed work (water circuit) has started.
Note: the demolition of the old building itself requires disclosure, and the wall should be demolished in advance. If there is a ceiling or a cultural wall, there is no need to shovel the wall skin in the future.
Step 2: After the cabinet manufacturer comes to the door to measure and draw the drawings, provide a detailed location map of the kitchen power board. The drawings are prepared for which socket is not suitable in the future, and it is clear who is responsible. During this period, such as replacing security doors, windows, gas pipelines, etc., can be carried out simultaneously.
Step 3: The marble manufacturer on the windowsill table will measure the financial processing stage.
Step 4: Wait for delivery, so that the merchant can receive the invoice before delivery. Please arrange a porter on the day of delivery.
Step 5: Locate the color of the door sample and wall paint.
Step 6: Do a closed water test in the bathroom.
Step 7: Check whether all air conditioning holes are suitable, and if necessary, re-drill holes before workers make walls.
Step 8: Buy hardware and simple lamps according to the list of materials listed by the carpenter; Contact the cabinet manufacturer to measure the net size after tiling.
Step 9: Customize the threshold stone.
Step 10: Buy your favorite lamps and sanitary wares and arrange their installation. Consider contacting the cabinet manufacturer for home installation.
Step 1 1: Install the door and sleeve.
Step 12: Install the floor.
Step 13: Install curtain cloth, do indoor cleaning, and start the key to enter the furniture.
For the owners, a clear schedule of fine decoration can play a controlling role.
Tubatu Online provides you with "every decoration quotation, 1-4 local decoration companies, 3 sets of decoration design schemes" and the decoration pit avoidance strategy for free! Click this link:/Zhu Ye /zxbj-cszy.php? to8to _ from = SEO _ zhidao _ m _ jiare & amp; Wb, you can get it for free ~
- Related articles
- What does a real estate company do?
- Which department should I call for commercial housing complaints?
- Is Hengyang Ecological Tianchen Worth Buying?
- I changed the property management company, do I still have to pay the property fee I owe?
- Is Gui Huayuan Bell Tower Phase IV a commercial house?
- stretch/extend as far as the eye can see
- How about Guoan Jiuzhou Technology Co., Ltd.?
- What is the telephone number of the sales office of Taihang Water Town in Lianxiang, Baoding?
- Is Guangzhou Huarun Land Park Uptown a rough house or a fine decoration?
- What grade is Jinan Evergrande Tianxi?