How to write the construction log?

Construction log number

Log 00 13

Remarks on weather conditions and maximum/minimum wind force

Sunny during the day, northwest wind 4-5, 9℃

Clear northwest wind at night -4℃

Production records: (construction site, construction content, mechanical operation, team production, production problems, etc. )

1 # building: 5 people from Zhang rebar class make 6-story section (f-g) (▽ x15.50-▽+18.00) wall rebar, and the rebar adopts GQ40 cutting machine and GW40- 1 bending machine. Four people from Li Qiang Woodworking Class set up five-story and two-level wall column formwork (column H- column L) (▽+13.00-▽+15.5), and the formwork was hoisted by FO/23B tower crane, with good effect. Five people in Zhang Ping's waterproof class do waterproofing of basement exterior wall (line A-B,1-8) (▽ ▽ ▽ ▽ ▽ ▽ ▽ ▽ ▽ ▽ ▽ 𗦕)

If you have any questions, you can write: 1 Concrete construction has been carried out on the roof panel and the fifth floor. Due to the power failure of the mixing station, there was no concrete supply from 14: 00 to 20: 00, and today's work plan was not completed. 2. Six-story wall ∮ 12 steel bars did not enter the site, and steel bar processing and binding stopped from 12: 00 to 18: 00.

Technical quality and safety work records: (technical quality and safety activities, inspection, evaluation and acceptance, technical quality and safety issues, etc. )

1. The technicians of the steel bar processing project department make technical and safety disclosure to Zhang's steel bar class. The Technical Disclosure Letter shall be signed by the receiver Zhang. The disclosure date is March 6, 20 1 1.

2. Li Quan, a technician of the basement waterproof engineering project department, made technical disclosure and safety disclosure to Zhang Ping's waterproof class. The technical disclosure was signed by Zhang Ping, the recipient of James Li, and the disclosure date was 2011March 6.

3, the basement waterproof construction operators have waterproof construction operation certificate after inspection. Waterproof coiled material has certificate of approval and re-inspection certificate.

4. Before the formwork erection of the five-story wall, the site supervisor, technical personnel of the project department and technical personnel of the construction team inspected the wall reinforcement binding, and the inspection results were qualified, so the next working procedure can be carried out.

Recorder Cao Fuli Date: 2065 438+0 1 03 06 Sunday.