Job Recruitment Website - Property management company - Time limit for a project extension application report
Time limit for a project extension application report
The application report is a tool for individuals or collectives to express their wishes and make demands to organizations, organs, enterprises, institutions or social groups. The following is the application report for extension of the construction period I collected, hoping to help you!
Application report for extension of construction period 1xxxxx Bureau of Foreign Trade and Economic Cooperation:
According to the construction contract between both parties, the safety maintenance project of xxxx Foreign Trade and Economic Cooperation Building undertaken by our company should be completed on 20xx 19 10/0/9. However, in the process of construction, the extension of relevant visas and contracts occurred, which led to the failure to complete the project as agreed in the contract. Now I will summarize and report the time difference in the construction process of our company:
1.20xx On July 3rd, both our company and your bureau received the Letter of Safety and Quality Rectification of Building Engineering from the Municipal General Safety and Quality Station, which stated: the safety appraisal of the main building structure has not been completed, and the original structure is unknown, so it is required to stop work in an all-round way. After being confirmed by the test data of your bureau and the testing unit, the supervision engineer issued a notice numbered 07, and resumed normal construction on August 7, 20xx. Directly affect the construction progress for 36 calendar days.
2.1At 20xx 10 on October 6, connect the typhoon forecast No.23 of the Central Meteorological Observatory. In order to prevent Taiwan from fighting against Taiwan, according to the actual safety situation, the project implemented a comprehensive shutdown measure. The typhoon caused serious floods in our city. The municipal government and the three defense headquarters have repeatedly told us not to go out easily on TV programs, focusing on typhoon resistance and drainage, and taking measures to suspend classes and work for schools and projects under construction. The flood disaster after the typhoon caused the project to stop working until 20xx year 65438+1October 12 for 7 calendar days.
3. In view of the actual situation, due to the need to dismantle the roof broadcast tower in the property, for the sake of safety, the construction period directly affected by our company is 7 calendar days from the end of May to the beginning of June in 20xx.
4. As the removal of the glass curtain wall of the whole building is not within the bidding scope, the owner requires our company to remove it with the materials, and the entire external wall construction must be stopped when the original glass curtain wall is removed. 20xx September 16 to 10/5, all glass curtain walls were demolished. During this period, the construction period of this project is delayed 19 calendar days.
To sum up, in the construction process, the overall construction progress of this project has been delayed for 69 calendar days, making it difficult to achieve the original planned construction period. All the above situations belong to the extension of the construction period in the contract. Therefore, please extend the contract period according to the actual situation on site, and take the actual period as the contract period of this project. Please leaders to give recognition!
I hereby report it.
Xxxxx group co., ltd
20xx65438+1October 16
Application Report for Extension of the Second Construction Period of Engineering Department of Guorunsi Food Co., Ltd.:
Thank you for your trust and support to our company, and we will undertake the interior decoration project of your office building. In order to ensure the high-quality and efficient completion of the project, we officially started construction on March 16. However, after the project department entered the construction site, the normal construction and progress of the project were seriously affected by the following problems:
1.On March 16, our company entered the site and found that the masonry and plastering processes of civil brick walls were not completed in a large area, which led to our lack of operation surface construction and the inability to organize effective construction according to the original construction plan and planned construction period, which increased the difficulty of our construction management;
Second, during the construction process, you proposed some changes to the drawing scheme, which made it impossible for us to carry out the construction of the changed parts, and also affected the construction of other parts, delaying the construction period;
3. Your application for payment of our project funds has been delayed repeatedly, and it has not been paid according to the application items, which has seriously affected our capital turnover. Labor costs and material costs have not reached the designated position for many times, and material suppliers have pledged goods or intermittently supplied goods for many times, thus delaying the construction period;
Fourthly, the glass curtain wall of the exhibition hall has not been completed so far, which has seriously delayed the completion date of our overall project.
On June 20th, we completely completed the renovation project of the east and west office buildings, and the first, second and third floors have been delivered to you for use. At present, it is impossible to enter the construction site because the glass curtain wall has not been completed and the shops in the urban area have been completed. In view of the above situation, I hereby apply to extend the construction period to 20xx65438+February 3 1, please reply!
Xxxxx group co., ltd
20xx65438+1October 16
3. Application report for extension of construction unit:
Supervision unit:
Thank you for your trust and support to our company, and our company will undertake your "xxx Garden Landscape Project".
In order to ensure the high-quality and efficient completion of the project, our company officially started construction on July 1 day of 20xx according to the terms of the contract.
However, since the project department entered your site, the following problems have seriously affected the normal construction and progress of this project:
A, the influence of the total package unit:
Due to the labor shortage of the general contractor, it was not completed in a large area; There is basically no working face in our department to construct, and it is impossible to organize effective construction according to the original construction plan, which increases the management difficulty of our department and causes many losses of slowdown and rework. So far, the civil construction process has not fully met the requirements of our construction conditions.
Second, the impact of water cuts:
As the general contractor (Nantong No.3 Construction Project) started to cut off the water supply to our department in the morning of July (2 1) in 20xx, the domestic water supply of our department was difficult, which led to the inability of our department to guarantee the life of workers, which led to the impetuousness of workers and the inability to organize construction normally. Please deal with it.
Third, climate impact:
Since mid-July, Beijing has been in the rainy season, which has prevented us from carrying out normal construction, disrupted the construction progress of the project and caused considerable human and material losses.
In view of the above situation, our department adheres to the engineering service concept of "thinking about what the owners think and being anxious about what the owners are anxious about"; Organize internal analysis seminars for many times, learn from the construction experience of excellent projects in the past, and combine with the actual situation of this project, adopt circuitous construction, cross construction and other operation schemes, try to let the construction team invest in the construction work and grab the working face construction; Corresponding finished product protection measures have been taken, but the project management cost and construction cost have also increased.
According to the requirements of high-quality engineering construction technology and cycle, and at the same time urging the owner to consider the quality and safety of the project, our department specially applies to your company to extend the project period by 15 days, and postpone the project completion time to September of 20xx 15 days.
Please give an answer from the leader of your company.
Thank you again for your support to our work.
Xxxxx group co., ltd
Xx,xx,XX,XX
;
- Previous article:Model essay on real estate project planning scheme
- Next article:Nishuo property
- Related articles
- What should the company's corporate culture do?
- What is the telephone number of Jiaozuo Ideal City Marketing Center?
- Where is Wuxi Haier Chengchuang Emerald Wenhua?
- In 2022, Sam Excellence membership card will not wash the car.
- Which do the property project manager and the boss driver choose to do?
- How to pay the rent and property management fee for the house rented by the company?
- Why didn't you provide a contact number in the recruitment information of Gongyi Employment Network?
- How many working days can the muck truck transport permit in Tongzhou District of Beijing come down?
- How to complain about the poor attitude of residential property service
- Comparison of Peace Paradise Community in Baiziwan Home