Backfill cushion construction scheme final

Special construction scheme of backfill cushion

I. Overview of the Project

Project Name: Jiangyin Lixin Phase V Resettlement House West Zone

Construction site: east of Hongqiao Road, south of Lixin Road and west of Huashan Road, Jiangyin City. Construction unit: Jiangyin Yongsheng Real Estate Development Co., Ltd.

Designer: MCC Tianchang International Engineering Co., Ltd.

Supervision unit: Jiangsu Waijian Construction Consulting and Supervision Co., Ltd.

Construction unit: Yixing Construction Engineering Construction and Installation Co., Ltd.

Project scale: 4#, 5#, 1 1#, 12#, 19#, 20# building frame shear wall 14 floor, 17#,/kloc-.

Structural form: frame, frame-shear structure

Second, the construction scheme

After the earthwork backfilling of the foundation of each main building in the west area of the fifth resettlement house in Jiangyin, the backfill soil does not have the mechanical foundation of the first floor wall column, the second floor beam slab formwork bent column and the outer scaffold column of each main building, so hardening measures must be taken on its surface. According to the actual situation on site, our project department takes measures to pour 70mm thick C 15 cushion on the 2m backfill surface of each main building and its surroundings to ensure the smooth construction and safe production of the project.

Yixing construction engineering construction and installation co., ltd

Jiangyin Lixin phase 5 resettlement Fang west zone projects department

20 12 September 17