How long is the simple renovation period of Shenzhen 140 square meters?

It is estimated that the normal renovation of a 140 square meter house will take two to three months.

65,438+00 days before commencement: make design scheme, select decoration company, put forward decoration contents and requirements, measure relevant data on the spot, draw detailed drawings, fully communicate with designers and determine the final scheme.

5 days before construction: Look at the budget contract, determine the materials to be used, preliminarily budget the home improvement expenses, compare the budget of the home improvement company, and sign the renovation contract.

2 days before construction: prepare before entering the site, contact the property management department, complete the necessary formalities, hand over the key of the builder, and pay the first decoration payment.

During the renovation, it will take about 50 days: structural demolition and renovation 1~2 days; Before house decoration, the structure is generally demolished and reconstructed according to the design scheme, and it usually takes 1~2 days for small and medium-sized units. If there is no such item, you can subtract this one.

5~ 10 days for hydropower transformation: hydropower transformation, i.e. slotting, wiring, pipe laying and acceptance. Generally, it takes 5~ 10 days, sometimes even longer, depending on the different complex conditions of the project.

The mud tile project takes about 15 days: the mud tile project includes kitchen and bathroom waterproofing, tile laying and other projects. According to the different tile paving area, the time required is different. It usually takes about 15 days. If the waterproofing fails to pass the acceptance, the time may be longer.

Woodworking is about 10 day: Woodworking includes ceiling, floor, background wall, furniture making, etc. It may take 20 days for a long time, and finished furniture may be used for a short time, and there is no wood-making project, which saves time.

The painting project takes about 65,438+00 days: the painting project mainly includes wall painting and wallpaper pasting. Because the paint generally needs to wait until the putty is dry before brushing the primer and topcoat, sometimes it needs to be brushed several times, and the construction period also needs about 10 days.

It takes about 5 days to finish the construction: the installation finishing stage includes the installation of various sanitary wares and cabinets. These installations can be carried out several times a day because there are no conflicts. So if the product comes into the market in time and is installed reasonably, it can be done in a few days.