Job Recruitment Website - Recruitment portal - (2008? Jingmen) 1000 kV UHV AC transmission demonstration project is the first UHV AC transmission and transformation project in China, with large capacity and low loss.

(2008? Jingmen) 1000 kV UHV AC transmission demonstration project is the first UHV AC transmission and transformation project in China, with large capacity and low loss.

The current in the line during normal transmission I = PU = 50000000000 w100000000 v = 5000 a,

P power loss on transmission line = i2r = (5000a) 2×10ω = 2.5×108w.

So the answer is: 5000; 2.5× 108.