3. Model clauses of rural highway construction contract
Model text of road construction contract 1
According to the actual situation of poor roads in our village, a standard gravel road will be built from our village to Xiaosijiajie, which will be contracted out by the village committee through public bidding. Shengli Village is Party A, and Yan Li is Party B. This contract is concluded through negotiation between both parties.
1. The gravel road from the village to Xiaosijia Street is 7 kilometers long.
Second, the quality standard must reach 7 meters wide, 25 centimeters thick, and the gutter 1 meter wide and 80 centimeters deep.
Three. The contract fee and project investment are 98,200 yuan, and Party B is responsible for the sand and gravel.
Fourth, the time for contracting for road construction, starting from February 2, 2000, 10, must be completed before 10/30, 2000, waiting for the joint acceptance at the rural level.
5. Road construction must be carried out as required and pay attention to safety. In case of any accident, Party B shall be responsible for solving it.
Liability for breach of contract of intransitive verbs. Both parties to the contract must abide by the terms of the contract and complete the project on time. Party A has the right to refuse to pay part of the contract fees as maintenance fees.
7. This contract is made in triplicate, one for each party, and one for the township government, which shall come into effect as of the date of signing.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Model essay on road construction contract II
Party A: (hereinafter referred to as Party A) Party B: (hereinafter referred to as Party B)
In order to ensure the smooth implementation of the _ village _ village highway construction project and complete the project on time with good quality and quantity, this contract is concluded through full consultation between Party A and Party B in accordance with the relevant provisions of the Economic Contract Law and the characteristics of this project:
I. Construction Project and Content of the Project
According to the project construction content and project construction plan, the total length of the project section is kilometers, the road width is 4 meters and the thickness is 20 centimeters.
Second, the project cost and contracting methods
The project cost is contracted to Party B according to the design kilometer, and the project cost is RMB. Settlement should be carried out according to the actual completed quantities.
Third, the engineering quality requirements and paving technology
1. Party B shall organize the construction in strict accordance with the technical standards and specifications of the gravel road project, take full responsibility for the quality of the project undertaken, and must reach the qualified project. According to the "standard for quality inspection and evaluation of gravel road" acceptance.
2. Party B must accept the supervision and management of Party A and the transportation department. Any violation shall be regarded as breach of contract, and all adverse consequences and responsibilities arising therefrom shall be borne by Party B. ..
3. Party B must carry out standardized construction in strict accordance with the construction procedures, and after completion, the construction unit and the district burden reduction office will handle the final project; District tax reform office and relevant departments jointly accept.
Fourth, the construction period
The construction period of this project is from June, 20_ 18 to July, 20_ 18. After the project is completed, the district will reduce the burden. Subject to the district tax reform office and the acceptance of the construction unit.
Verb (abbreviation for verb) Rights and obligations of both parties.
1. Party A and Party B have the right to supervise each other's performance of the first paragraph of this contract.
2. Party A has the right to supervise the whole process of Party B's construction quality, and Party B must obey the instructions and accept the supervision and inspection.
3, quality inspection personnel should be serious and responsible for the project, stick to their posts, adhere to principles, and negotiate to solve problems existing in the construction process at any time.
4. Party A shall provide necessary facilities for the construction according to the needs of the project.
5. Party A's obligations
(1) Party A has the obligation to be responsible for on-site coordination.
(2) Pay the project funds according to the contract (after the burden reduction office allocates funds, the project funds will be allocated to Party B).
6. Party B's obligations
(1) shall be fully responsible for project quality, construction period and construction. , do all the preparatory work before construction, and complete the construction task on time with good quality and quantity. After completion, Party B shall provide completion data and apply for completion acceptance.
(2) The construction must be carried out in strict accordance with the procedures of engineering specifications, and it is not allowed to cut corners or lower the engineering standards, otherwise Party A has the right to require Party B to rework or stop work.
(3) Party B shall take full responsibility for construction safety, ensure safe and civilized construction, and take various safety measures to educate construction personnel to prevent various safety accidents; In case of accident, all responsibilities shall be borne by Party B. ..
Alteration and termination of intransitive verb contract
1, change of contract
If it is really necessary to increase or decrease the quantity of works due to the needs of the project, the contract can only be changed after consultation between Party A and Party B, and the contract cannot be changed unilaterally.
2. Termination of the contract
(1) Party B fails to start work within three days after the notice of commencement is issued;
② Party B fails to construct according to the contract and quality requirements during the construction;
③ During the construction of Party B, Party A ordered Party B to rectify within a time limit due to quality problems, but Party B failed to rectify;
(4) After the project is completed, this contract will be automatically terminated after the warranty period expires and the project payment is paid. Under any of the above circumstances, Party A has the right to request the termination of the Contract.
VII. For matters not covered in this contract, both parties can sign a supplementary contract through consultation, and the signed supplementary contract has the same legal effect as this contract.
Eight. This contract is made in duplicate, one for each party, and shall come into effect as of the date of signature by both parties.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Model road construction contract 3
Party A:
Party B:
In order to meet the needs of Dingzhou Shounong Group project, it is necessary to build a temporary construction route. The starting point of the temporary section is the northwest of Shahe Bridge, and there is no road in the east, and the end point is the edge route of the silage cellar project. It is determined to use the local sand and gravel materials provided by Party A as the road construction materials, and entrust Party B to build temporary sections according to Party A's requirements. In order to clarify the contents of the project and the responsibilities of both parties, the following terms and conditions are reached through consultation between both parties:
I. Content and scope of the project.
1, starting point and ending point are northwest of Shaheqiao, there is no road in the east, and the end point is silage.
On the edge of the cellar project, there are three parts in total:
Section 1: 947m _ 8.5m _ 0.25m (length _ width _ thickness);
Section 2:1551m _ 3.5m _ 0.15m (length _ width _ thickness);
Part III: 700m× 7.5m× 0.25m (length× width× thickness)
2. Party B is responsible for providing machinery, manpower and technical personnel.
3. Engineering and cost.
According to the above-mentioned quantities, through negotiation between both parties, Party B contracts this contract with RMB (in words) one hundred thousand Yuan only (including tax).
Second, the construction technology
Strictly abide by the national construction specifications and technical standards and meet the requirements of Party A. ..
Third, the responsibilities of both parties.
1. Party A's responsibilities:
Responsible for the command, supervision and management of project quality, safety production, project progress and ingredients.
2. Party B's responsibilities:
(1) Respect and obey the owner, be fully responsible for the project quality, and ensure that it reaches the excellent grade or above.
(2) Strengthen the safety production education of the construction team, carry out the construction in strict accordance with the operation specifications, do not connect the circuits and pipelines indiscriminately, do not install power sockets without permission, do not forcibly violate the rules and regulations, and strictly put an end to other safety accidents such as fires. Otherwise, Party B shall bear all responsibilities arising therefrom.
(3) Workers must enter the construction site in a civilized and safe way, and clean up the site after the project is completed.
(4) Sufficient construction personnel and technical force must be ensured, with stable quantity and high work efficiency, otherwise problems such as lagging teaching staff and project quality caused by this shall be borne by Party B. ..
(5) Party B guarantees that Party A will not bear all responsibilities for any personal injury or property loss, and Party A will not bear any public prosecution, accusation, claim liability and possible related expenses caused by Party B and its construction personnel.
Verb (abbreviation of verb) engineering quality and acceptance standard
The project quality shall conform to the current national acceptance standards. Must reach the excellent level of national or professional quality inspection and evaluation. Because Party B is blind and reckless; If the construction progress does not meet the operation specifications, resulting in the project quality does not meet the design requirements and unqualified quality, Party A may require Party B to stop work or rework, and the cost of rework shall be borne by Party B, and all the material waste and economic losses caused thereby shall be compensated by Party B, and the construction period shall not be postponed.
Intransitive verb payment method
After the project is completed and accepted by Party A and the supervisor, the project payment shall be paid.
Seven. Party A has the right to interpret the above terms of this agreement.
Eight. This agreement is made in duplicate, each party holds one copy, which has the same legal effect. This agreement shall come into effect as of the date of signature and seal by both parties, and shall be terminated after the above-mentioned construction project for which Party B is responsible is completed.
Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _
Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Three related articles on rural highway construction contract model;
★ The latest model essay of road construction contract 3.
★ 3 road construction contracts
★ 4 copies of rural highway construction contract model.
★ 3 simple versions of road construction contract templates
★ Five simple rural highway construction contracts
★ 3 latest road construction contracts
★ 4 copies of rural highway construction contract model
★ Model rural road hardening contract
★ Rural Highway Construction Contract
★ 4 copies of common rural highway construction contract template
- Previous article:Wuhan Jinniu pipeline industry has difficulties in survival.
- Next article:South China Normal University Shanwei Campus Code
- Related articles
- Master's treatment of Phoenix Media Publishing House
- Sen lives in the Garden of Eden-Tengchong Phoenix Baoji.
- Tancheng county Zhong Fang Unicom business hall landline number
- What about Yantai Guhe Electrical Equipment Co., Ltd.
- Where is Wuhu department store wholesale market?
- Should the merchant inform the urban management when changing the plaque?
- Sotheby’s auction house job benefits
- Peng Yue Bar Recruitment Information in Pingcheng District of Datong City, how about Peng Yue Bar in Pingcheng District of Datong City?
- Where can Nanchang electric welder learn?
- What are the skills of China Bank's recruitment interview and what should I pay attention to?