Background (1)

A construction enterprise undertook the construction task of a six-story house. According to the responsibilities stipulated in the project management target responsibility book, the project manager of the project owner organized relevant personnel to complete the preparatory work such as determining the project organizational structure mode and compiling the construction organization design. During the construction of the second floor, the station supervisor found that the construction party did not operate according to the requirements in the construction organization design, and there were quality hazards.

Answer the following questions according to the background (1).

1. Among the following options, () is not the basis for compiling the responsibility book of project management objectives.

A. Project contract documents

B. Project management implementation planning

C. Management system of the organization

D. management policies and objectives of the organization

2. The authority of the builder's project manager in the implementation of this project is ().

A. Establish a project management department

B. Develop internal compensation methods

C. signing a contract

D. Selecting subcontractors

3. The project organization structure model reflects the () in the organization system.

A. Division of management functions of various departments

B. Command relationship between departments

C. Logical relationship between various tasks

D. Tasks of each subsystem

4. When preparing the construction organization design, the following items should be determined first ().

A. structural diagram

B. Construction progress plan

C. Construction plan

D. Construction preparation work plan

5. The webmaster found the problem to report to ().

A. supervision engineer

B. Quality inspector

C. Owner's on-site representative

D. project technical director

Background (2)

In order to ensure the realization of the project objectives and facilitate the organization and management of the project, the subway 1 line project in a city is divided into subsystems such as construction, depot, mechanical and electrical equipment engineering, preliminary engineering and operation preparation, among which Company A undertakes the civil construction task. In the project structure analysis stage, Company A determined and drew the project structure chart, organization structure chart, contract structure chart and workflow chart. According to the construction risk appraisal report of the project, Company A chose to insure the engineering geological conditions risk with the insurance company. The implementation of the project has been delayed. After technical personnel's demonstration, the project manager made a final decision to choose new construction machinery to replace the original construction machinery.

According to the background (2), answer the following questions.

6. Among the following factors that affect the realization of subway project objectives, the decisive factor is ().

A. Bonuses

B. Methods

C. organization

D. tools

7. The division of subway engineering subsystems is () in the construction management organization design work.

A. Division of quality responsibility

B. Workflow definition

C. Project structure decomposition

D. Definition of construction scope

8. Reflect all subsystems of the project is ().

A. Project structure diagram

B. Organization chart

C. Contract structure diagram

D. Work flow chart

9. A company's risk coping strategy for insurance companies is ().

A. Risk aversion

B. Risk retention

C. Risk diversification

D. Risk transfer

10. A company's practice of replacing the original construction machinery with new construction machinery belongs to () in the rectification measures for dynamic control of project objectives.

A. Organizational measures

B. Management measures

C. Economic measures

D. Technical measures

Background (3)

An independent earthwork excavation project is priced by bill of quantities. As stipulated in the construction contract of the construction project: the estimated project quantity in the contract is 300,000 cubic meters, and the unit price is 35 yuan/cubic meter; After completion, the project price shall be settled according to the quantities confirmed by the owner; When the actual engineering quantity exceeds 20% of the estimated engineering quantity, the excess shall be settled according to 30 yuan /m3. In order to control the construction cost, the construction project management department has formulated a series of management measures: organizing large earthwork excavation machinery to enter and leave the site in time, making a scientific construction operation plan, checking the construction machinery before each shift, strictly controlling the cost and doing a good job in cost analysis.

After the completion of the project, the amount of work confirmed by the owner was 400,000 cubic meters, and the construction project management department submitted relevant claims and settlement materials in time.

According to the background (3), answer the following questions.

1 1. According to Cost Composition of Construction and Installation Engineering (JB [2003] No.206), the entry and exit expenses of large earthwork excavation machinery belong to ().

A. Construction and installation engineering machinery use fee

B. Cost of mechanical measures for construction and installation works

C. Management fees of construction enterprises

D. Other costs of engineering construction

12. When the construction project intends to prepare the operation plan, the most convenient quota basis is ().

A. Construction quota

B. Budget quota

C. Budget estimate quota

D. Budget estimation indicators

13. The cost control of the construction project should run through the whole process of the project, specifically the stage ().

A. from construction bidding to completion acceptance.

B. From project initiation to completion acceptance.

C. from the beginning of the project to the expiration of the warranty period.

D from the beginning of foundation construction to the end of main body construction.

14. From the point of view of artificial quota time composition, the time required to check the construction machinery before each shift belongs to ().

A. Basic working hours

B. Ready to finish working hours

C. Inevitable interruption time

D. Auxiliary working hours

15. When comparing and analyzing the budgeted cost, target cost and actual cost of earthwork excavation, the target cost comes from ().

A. Bid quotation cost

B. Quantity and unit price listed in the construction task list

C. the project intends to prepare the construction budget.

D. Design budget prepared by the design unit

16. When the project intends to calculate the claim cost, the most accurate method is ().

A. Budget cost method

B. Total cost method

C. Revising the total cost method

D. Actual cost method

17. The total earthwork excavation price that should be settled after the project is completed is () ten thousand yuan.

A. 1 200

1 350

C. 1 380

D. 1 400

20. The unit price of the foundation division project (550 yuan /m3) does not include () required for the project construction.

A. Labor cost

B. Material cost

C. concrete formwork and support fee

D. Construction management fee

2 1. The physical and mechanical properties of the steel required for the foundation division project should be inspected before use, and the inspection fee belongs to ().

A. Material cost of construction and installation project

B. Cost of construction and installation measures

C. Management fees of construction and installation engineering enterprises

D. Other costs of engineering construction

22. The construction project intends to set up the site office costs should be from ().

A. Material cost of construction and installation project

B. Management fees of construction enterprises

C. Construction and installation engineering measures fee

D. Management fee of the construction unit

23. According to the function of the cost plan, the planned value (400 yuan /m3) of the basic division project determined by the construction project management department and its decomposition index belong to the () cost plan.

A. Strategic

B. Competitiveness

C. guidance

D. enforceability

Background (5)

An engineering general contracting enterprise undertakes the general contracting business of a large-scale transportation hub project and signs a general contracting contract with the owner. In order to achieve the overall construction progress goal proposed by the owner, the general contractor of this project has carried out the following series of work:

(1) Analyze and demonstrate the possibility of achieving the general progress goal, and prepare the general progress outline demonstration document;

(2) The overall project schedule is compiled, and a schedule system consisting of schedules with different compilation depths, different functional requirements and different planning cycles is formed;

(3) The purpose and task of general contractor's schedule control are defined, and various measures of schedule control are put forward.

According to the background (5), answer the following questions.

24. The self-calibration of the overall progress of the construction project is determined in the () stage of the project.

A. decision-making

B. Preparation before design

C. design

D. architecture

25. Before controlling the overall progress of the project, the general contractor should first ().

A. determine the overall progress goal of the project

B. analyze and demonstrate the possibility of achieving the goal

C. Clarify the purpose and task of schedule control

D. prepare the overall project schedule.

26. The demonstration of the overall progress goal of the construction project includes: ① determining the work code of the project; ② Investigation and data collection; ③ Analyze the project structure; ④ Analyze the structure of the schedule planning system. Its working steps are ().

A.①-②-③-④

B.②-①-④-③

C.①-④-②-③

D.②-③-④-①

27. The core work of large-scale construction project total progress demonstration is ().

A. define schedule control measures

B. analyze the main factors that affect the construction progress and bid realization.

C. Prove the possibility of achieving the general schedule goal by compiling the general schedule outline.

D. Prepare progress plans at all levels.

28. The following schedule control measures, belongs to the organizational measures is ().

A. Work out the workflow of schedule control

B. Choose a reasonable contract structure to avoid too many contract interfaces, which will affect the work progress.

C. Analyze the risks affecting the progress and take corresponding measures to reduce the risks of unbalanced progress.

D. Choose a scientific and reasonable construction scheme, make a technical and economic analysis of the construction scheme, and consider its influence on the progress.

Background (6)

A construction enterprise signed a construction contract with the owner. The construction progress plan approved by the supervision engineer is shown in the figure (time unit: days).

According to the background (6), answer the following questions.

29. The construction progress plan approved by the supervision engineer is () days.

A.2 10

B.245

C.280

D.300

30. In the above construction network plan, the earliest commencement time and the latest commencement time of exterior wall decoration project are () days respectively.

A. 185 and 205

B. 185 and 235

C.205 and 235

D.235 and 255

3 1. In the above construction network plan, the total time difference of elevator installation and commissioning is () days.

A.30

b60

C.90

D. 120

32. The following statement about network planning is correct ().

A. the network plan has only one key line.

B. A network plan may have multiple critical lines.

The C line composed of non-critical work is called non-critical line.

D. circular loops are allowed in the network plan.

33. In the network plan, the key work refers to ().

A. the operation with the smallest total time difference

B. Work with minimum free time difference

C. waveform lines are not used in time scale network planning.

D. Work with the longest duration

34. The dotted line in the double code network diagram indicates ().

A. Degree of resource consumption

B. During working hours

C. Logical relationship between jobs

D. Non-critical work

Background (7)

The plane of an industrial building is circular, and the construction measurement accuracy is required to be high. The roof is made of steel structure, some steel products are imported from abroad, and the main materials such as steel bars and cement are supplied by the owner, and the construction unit is responsible for inspection. In order to ensure the quality of the project, the construction unit has formulated a detailed quality control plan. The concrete schemes of material quality control, measurement control and technical disclosure are put forward.

According to the background (7). Answer the following questions.

35. Materials, semi-finished products or components delivered to the construction site shall have products () and technical specifications.

A. factory certificate

B. Three Guarantees Certificate

C. Inspection certificate

D. Certificate of approval

36. In all kinds of factors affecting the construction quality, the foundation of engineering quality is ().

A. Construction management

B. Material

C. Building technology

D. Construction method

37. Measuring the length and diameter of imported steel bars belongs to () inspection.

A. in writing

B. Appear

C. physics and chemistry

D. lossless

38. The inspection degree of imported steel should be ().

A. Exemption from inspection

B. Sampling inspection

C. Comprehensive inspection

D. retake the exam

39. The construction survey control scheme should be implemented after the approval of ().

A. Project manager

B. project technical director

C. Person in charge of the construction enterprise

D. The person in charge of the supervision enterprise

Background (8)

A steel structure project; The following events occurred during the construction.

Event 1: Due to the serious delay of the foundation project, the person in charge of construction failed to control and inspect according to the quality standards in order to catch up with the construction period, resulting in serious deformation of the concrete formwork, and spent 50,000 yuan to make up for the defects.

Event 2: Due to the inaccurate elevation, the floor elevation and height are wrong and the defect cannot be remedied.

According to the background (8). Answer the following questions.

40. In the process of construction, the results of construction survey recheck shall be submitted to () for recheck and confirmation before the subsequent construction of related processes can be carried out.

A. Project manager

B. supervision engineer

C. owner's technical director

D. project technical director

4 1. Before the construction of steel structure engineering, the technical disclosure scheme shall be prepared by the project technicians and implemented after being approved by ().

A. Project manager

B. Technical director of supervision unit

C. technical director of the construction unit

D. project technical director

42. Before the steel structure engineering construction, the technical director of the project shall make a technical disclosure to the construction director.

A. in writing

B. exemplary

C. routine

D. oral

43. The use of steel structure hoisting machinery should implement the management system of ().

A. time, machines and people.

B. Set up machines, personnel and post responsibilities.

C. assign personnel, posts and work order.

D. set the time, personnel and work order.

44. From the accident level, the event 1 belongs to () quality accident.

A. General

B. serious

C. meaningful

D. Particularly important

45. From the point of accident responsibility, event 1 belongs to () responsibility accident.

A. Guidance

B. Operation

C. organization

D. technology

46. In order to ensure that similar accidents will not happen in future construction, the construction unit should strictly implement the "three inspections" system, namely ().

A. Construction self-inspection, supervision re-inspection and government supervision

B. Self-inspection, mutual inspection and handover inspection

C. Pre-inspection, process inspection and completion inspection

D. written inspection, experimental inspection and experimental inspection

Background (9)

For an industrial plant construction project, Company A is the general contractor and Company B is the steel structure installation subcontractor. In the process of hoisting workshop crane beam with crawler crane, an installer fell from the sky and died on the spot. During the accident investigation, the following conditions were found.

(1) Before the accident, safety measures were taken according to the construction scheme, including setting safe operation platforms on the columns at both ends of the crane beam, and there was no steel wire rope between the columns.

(2) The accident happened as follows: After the crane beam was hoisted in place, it was found that the hook releasing device of the spreader was out of order, and the workers left the operating platform to release the hook at the crane beam. At this point, the crane driver misoperated and suddenly lifted the hook, causing the crane beam to turn over and the workers to fall.

(3) The worker is an employee of Company B, who has received post safety technical education as required, but has not applied for accident insurance. His signature was not found on the safety technical disclosure record of that day. When he fell, he wore a seat belt and the hook rope was neatly wrapped around his waist.

According to the background (9). Answer the following questions.

47. Before going to work every day, the person responsible for safety technical disclosure to workers is ().

A. Captain

B. foreman

Project leader of C.B company

D. Technician of a company's project department

48. China's relevant production safety law stipulates that the person who must apply for accidental injury insurance for equipment installation workers and pay the insurance premium is ().

A. Project construction unit

B. Company A

C. company b

D. Local labor department

49. After receiving the accident report, the competent department of the enterprise and the labor department shall immediately report it step by step according to the system ().

The person in charge of the enterprise and the labor department and public security department where the enterprise is located

B. County and municipal departments in charge of enterprises and labor departments

C. Departments in charge of enterprises and labor departments in all provinces, autonomous regions and municipalities directly under the Central Government

D. Relevant competent authorities and labor departments in the State Council

50. The accident investigation team thinks that the dead workers have unsafe behaviors in the accident, which means ().

A. Failing to apply for accident insurance

B. Leave the safe operation platform and untie the crane beam.

C. Failing to sign the safety technical disclosure record of that day

D. The safety belt hook is not reliably hung on the safety rope.

Background (10)

A large-scale project is located in the suburbs of the city, and the surrounding roads belong to general sections. Temporary accommodation and canteen for construction are set within the site fence. Before construction, the construction unit shall formulate technical measures for construction safety and make technical disclosure to relevant personnel. Due to the tight construction period, the construction unit applied to the relevant departments for night construction and promised to ensure civilized construction.

According to the background (10). Answer the following questions.

5 1. According to the construction safety technical disclosure system, () is responsible for organizing relevant departments to disclose safety technical measures to the project management department and subcontractors.

A. technical director of the construction unit

B. Technical director of supervision unit

C. Head of security department of general contractor

D. general contractor engineer

52. According to the Construction Site Management Regulations, the enclosure height of the construction site shall not be less than () meters.

A.3

B.2.5

C.2

D. 1.8

53. There are more than () people in the temporary canteen of this project, so a simple and effective grease trap should be set up to discharge the generated sewage into the municipal sewage pipeline after passing through the grease trap.

A.50

b30

C.90

D. 100

54. According to the national standard "Noise Limit at Construction Site" (GB l2523-90), the noise limit of concrete supporting machinery at night is () dB (a) O.

A.50

b55

65

Cao 75

Background (1 1)

In the comprehensive construction project, the owner contracts the whole civil engineering to the contractor, contracts the electromechanical installation project to the contractor, and entrusts the supervision company to supervise the project. The owner signed construction contracts with contractor A and contractor B respectively according to the Construction Contract of Construction Project (Model Text) (GF GF-99—020 1+0). In the construction contract signed by the owner and contractor A, it is agreed that part of the building materials and equipment will be supplied by the owner. Party A's contractor subcontracts the labor operation of the main project construction to Party C's labor subcontractor for completion. The project was finally completed as scheduled. Contractor A submitted the completion acceptance report to the owner in April 1 year, and the owner did not organize the completion acceptance until May 20th due to the enterprise restructuring, and the acceptance passed. On may 25th, contractor a obtained the certificate of completion acceptance, and on June 1 day, he went to the construction administrative department to handle the relevant filing procedures.

According to the background (eleven), answer the following questions.

55. The project construction contract mode belongs to ().

A. Parallel contracting

B. General construction contract

C. General subcontracting of construction

D. Construction general contracting management

56. The actual completion date of this project is ().

A. April 1

B. 20 May

C. 25 May

D. June 1

57. In the process of construction, the progress is delayed due to Party A's own reasons, and Party A puts forward and implements measures to speed up the progress according to the requirements of the supervision engineer, then ().

A contractor a has the right to request the contract price of additional emergency measures, and the supervision engineer is responsible for the effect of emergency measures.

B contractor a has no right to request additional contract price for emergency measures, but the supervision engineer shall be responsible for the effect of emergency measures.

C contractor a has no right to ask for additional contract price due to emergency measures, and the supervision engineer is not responsible for the effect of emergency measures.

D the additional contract price of emergency measures shall be borne by the owner, and the supervision engineer shall be responsible for the effect of emergency measures.

58. During the construction of external wall thermal insulation project, after contractor A suspended the construction according to the requirements of the supervision engineer, the supervision engineer failed to reply to the application for resumption of work put forward by contractor A in time, which led to contractor A's failure to resume work in time, and the liability for breach of contract was ().

A. supervision engineer

B. Owner

C. contractors

Special zone labor subcontractor

59. Before using the materials and equipment supplied by the owner, the personnel responsible for inspection or test and those who bear the inspection or test expenses are () respectively.

A. Industry and material suppliers

B. owners and contractors a

C. supervision engineer and owner

D. Contractor A and Owner

60. In the process of concealed engineering construction, the contractor shall, after completing the self-inspection, notify the supervision engineer in writing for acceptance () hours before concealment.

A. 12

b24

C.36

Grass 48

Background (12)

A contractor obtained the general contracting task of a construction project through bidding, and signed the general contracting contract according to the Construction Contract of Construction Project (Model Text) (GF-99-020 1). A contractor subcontracts the construction services of the main structure project to B labor subcontracting company, and signs the labor subcontracting contract according to Construction Labor Subcontract (Model Text) (GF-2003-02 14). The responsibilities and obligations of the contractor are stipulated in the general contract, and the pricing method of the contract is unit price contract. During the construction period, the following two incidents occurred.

Event L: On April 5, 2008, when the supervision engineer checked the construction quality of the roof waterproofing project, it affected the normal construction and the inspection result was unqualified.

Event 2: After the roof construction was completed on May 15, the supervision engineer doubted the quality of the waterproof project in a certain part of the gutter and asked for stripping and re-inspection. Contractor A stripped it as required, and the inspection result was qualified.

During the construction, according to the analysis results of contract execution deviation, Contractor A took measures such as adjusting the work plan and workflow, corrected the contract deviation, and completed the construction task as planned.

According to the background (XII), answer the following questions.

6 1. For the event 1, () shall bear the losses that affect the normal construction.

A. contractors

B. supervision engineer

C. Owner

D. supervision engineer or owner

62. For event 2, the following statement about contractual liability is correct ().

A. The Owner shall bear all the extra contract prices arising therefrom, and the construction period will not be postponed.

B the owner shall bear all the additional contract price arising therefrom, compensate the losses of the contractor, and postpone the construction period.

C all expenses arising therefrom shall be borne by the contractor, and the construction period shall be postponed.

D all expenses arising therefrom shall be borne by the supervision engineer, and the construction period shall be postponed.

63. After all subcontracting work is completed, Party B's subcontracting company shall submit complete settlement materials to Party A's contractor within () days after Party A's approval, and apply for final settlement.

Answer 7

B 14

C.2 1

Cao 28

64. For unit price contract valuation method, the basis for determining the settlement project payment is ().

A. Actual quantity and actual unit price

B. Contract quantity and contract unit price

C. Actual quantity and contract unit price

D. Contract quantity and actual unit price

65. Compared with the pricing method in lump sum contract, the characteristic of unit price contract is ().

A. the risk of the owner is small, and the contractor bears more risks.

B the bidder who can easily and quickly determine the lowest price when evaluating bids.

C it can greatly arouse the enthusiasm of the contractor in the construction progress.

D. The workload of operation coordination is heavy, which is not conducive to investment control.