I want to build a liquefied gas station. What are the procedures? (Address is Biyang County, Zhumadian City, Henan Province)

First of all, go to the local construction Committee to set up a project, and handle the land use certificate and red line map of the land construction planning department.

Go to the local fire brigade to check the overall layout of the station.

Then regional urban construction gas station construction examination and approval, environmental protection department for examination and approval,

Then go to the regional technical supervision bureau: boiler and pressure vessel inspection department

Notify the approval of pressure vessel and pressure pipeline drawings.

Then you can build a station.

The cost of building the station includes: installation materials for liquefied gas storage tanks.

Installation and design costs, land use infrastructure

There are also hospitality expenses of relevant units that cannot be left.

So a small liquefied gas station is worth 60w RMB!

If you don't understand anything, please contact QQ:7 102349 19.