When will the construction of Rutongsu Hunanxun to Changxing start?

August 25, 2022. According to the relevant information, construction will start on August 25, 2022, and it will be completed and opened to traffic in 2026 or 2027. The Huzhou section of the line starts from Nanxun District and ends at Changxing Station, with a total length of 64.9km, a total of 11 stations, and an average station spacing of 5.9km. The permanent land acquisition for this project is about 3096.31 acres, the temporary land acquisition is about 1024.32 acres, and the demolition of residential houses is about 14.28 acres. Ten thousand square meters, about 152,900 square meters of factory buildings will be demolished; the estimated total investment of the project is about 27.6 billion yuan, and the construction period is about 54 months.