Job Recruitment Website - Job information - Exterior wall coating renovation contract

Exterior wall coating renovation contract

Exterior wall painting and renovation contract model house (7 selected articles)

In today's developing world, more and more scenes and occasions need to use contracts, and signing contracts can balance the equal status of both parties. There are different types of contracts, and of course, they also have different purposes. The following are the exterior wall coatings and renovation contract samples (7 selected articles) I have compiled for you, hoping to help you.

Exterior wall coating renovation contract 1 Party B:

Party A:

The exterior wall decoration of Hongshuitang House is contracted by Party B. In order to clarify the responsibilities of both parties, this contract is hereby concluded and both parties shall abide by it:

I. Obligations of Party A:

1. Party A prepares raw materials for Party B's construction and supplements the required raw materials according to the progress of the project.

2. Party A shall provide Party B with water, electricity and ancillary facilities needed for decoration.

3. Party A lays bamboo rafts for Party B's construction site.

4. Party A is responsible for coordinating various relationships in the construction process.

Two. Scope of construction of Party B

1, leveling wall with external wall powder and coarse sand.

2. Stick cultural bricks and tiles on the external wall according to the drawings.

3. Corrugated tiles or S-shaped tiles should be attached to sloping surfaces and sloping roofs.

4. Mosaic ceiling

5, balcony gourd

Three. Obligations of Party B

1. Cover with cement, lime, etc. Before work or rain, put away items that are easy to be lost and damaged, and turn off the water and electricity.

2. The proportion of sand meets the quality requirements, saves raw materials, and is used now, leaving no mortar and cement slurry overnight.

3. Pay attention to safe construction and civilized construction. Party B shall be fully responsible for the safety of itself and its employees, and Party A shall not be responsible for it.

Fourth, the project cost:

Paint and paste tiles, mosaics, glazed tiles, etc. And settled in 42 yuan per square meter.

Verb (abbreviation for verb) Terms of payment:

Check out and pay after completion.

Other agreements on intransitive verbs:

1. In case of any change during construction, both parties shall communicate with each other and reach an agreement before construction.

2. Matters not covered in this contract shall be settled by both parties through consultation.

3. This contract is made in duplicate, one for each party, with the same legal effect. Sign by both parties.

Signature of Party A:

Signature of Party B:

Date:

Renovation contract II Party A's exterior wall coating:

Party B:

Party A undertakes the renovation of floors 9-22 and 23-24 of Kyoto Haoting. After consultation, both parties agree to contract the external wall decoration project to Party B in the form of no material contract. In order to facilitate the construction management and determine the responsibilities and settlement methods of both parties, the following clauses are formulated for both parties to implement.

I. Responsibility of Party A

1, responsible for providing notices of changes related to construction drawings, projects and projects;

2, responsible for coordinating the use of lifting machinery.

3. Provide relevant materials to be present.

4. Responsible for construction technical disclosure and safety technical disclosure.

Two. Party B's responsibilities

1, in the process of construction, the construction must be carried out in strict accordance with the construction drawings and the current relevant national codes and standards, so as to ensure that it conforms to gb502 10-200 1 Code for Quality Acceptance of Building Decoration Engineering (Decorative Engineering), and the tile is free from hollowing and cracks, the veneer is vertical and smooth, the angle of yin and yang is square, and the joints are straight. In order to ensure the quality of the project, it must conform to the relevant acceptance specifications. Once the on-site technicians find problems such as water seepage and falling, Party B shall be fully responsible for compensation, and Party B shall be responsible for compensation for reworked materials.

2. Construction safety: Before the project starts, it is necessary to carry out safety knowledge education, pay attention to their own safety and the safety of others, and educate construction personnel to abide by safety technical specifications. Ensure safe production and civilized construction, and put an end to safety accidents. In case of safety accident, Party B shall be responsible for its responsibilities and expenses, and Party A shall not bear any responsibilities and expenses.

Third, the construction progress

Party B must guarantee the construction progress of the project and carry out the construction in strict accordance with Party A's construction progress. If the delay is one day, the penalty will be 1 1,000 yuan, and so on. The timetable is detailed.

Fourth, the settlement method

Settle the spreading area of construction projects, and calculate scattered projects such as lines, beams and columns according to the actual spreading area. According to the actual expanded area of RMB/m2, excluding the area of doors and windows, including the scope of work such as mortar mixing, mortar transportation and cement mortar priming, Party B shall not do other decorative works such as convex window surfaces and bottom surfaces that do not stick porcelain surfaces.

Verb (abbreviation for verb) to pay

After the external wall starts, borrow meals in advance every 10 day. At the end of the month, 80% of the prepaid salary will be temporarily borrowed 10 yuan /m (including prepaid meals). After the external wall is pasted, it will be paid to 80% of the engineering quantity, 90% after the completion acceptance, and the remaining 10% will be paid five months later.

Other matters of intransitive verbs

1. During the construction of this project, Party B shall be responsible for all daily life and accommodation, and Party A shall not bear any expenses.

2. Matters not covered in this contract shall be settled by both parties through consultation.

3. This contract shall come into effect as of the date of signing, and neither party shall breach the contract. If one party breaches the contract, its economic losses shall be borne by the breaching party.

4. This contract is made in duplicate, one for each party.

Party B:

Party A:

Date:

House exterior wall coating renovation contract 3 Party A:

Party B:

Through negotiation between Party A and Party B, Party A contracted Party B the construction of indoor bricklaying surface of external wall opposite Jinjiang XX Factory. The specific terms are as follows:

First, the construction period:

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Second, the contract price:

1.32 yuan exterior wall shall be primed once per square meter (two or three times shall be counted separately), bricklaying, seam wiping and corner plastering shall be counted separately (wall cleaning shall be counted separately).

2. Draw a square 6 yuan indoors.

3. 25 yuan with a square roof.

4. The roof should be waterproof, an ordinary 35 yuan (special waterproof material)

Three. Payment terms:

Cash payment for the project and equipment pre-purchase: RMB. After the shift enters the site, it shall pay the living expenses of 10000 yuan every10 day, and pay 80% of the project payment according to the contract requirements. (If the payment is not in place, Party B has the right to stop the construction. ) After other projects are completed, the balance will be paid in full.

Four. Party A's responsibilities:

1, responsible for the supply of main materials such as ceramic tiles and cement.

2. Be responsible for connecting the power supply and water source. (Party B can purchase materials on its behalf)

Verb (abbreviation of verb) Party B's responsibilities:

1. Strictly implement the construction specifications and safety operation procedures, and Party B shall be responsible for all safety accidents during the construction. (Note: If it is not an operation problem but a shelf problem, Party A will be responsible for all the problems. )

2. Carry out the construction according to Party A's requirements to ensure the decoration quality.

3. Party B shall be responsible for rework and repair of quality problems caused by construction during decoration and warranty period, and the expenses shall be borne by Party B. ..

5, the amount of ceramic tile shall not exceed two percent.

(Note: If the above changes and rectifications are agreed by both parties, the actual construction area shall prevail. ) This contract is made in duplicate, one for each party, and shall come into effect after being signed.

Party A (official seal): _ _ _ _ _ _

Party B (official seal): _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

House exterior wall coating renovation contract 4 Party A: (hereinafter referred to as Party A)

Party B: (hereinafter referred to as Party B)

Party A contracted the external wall tile and decorative plastering project attached to the external wall of the commercial and residential building in Beiliu Lane to Party B. In order to make Party A and Party B clear their responsibilities and obligations and effectively protect their own interests, according to the relevant provisions of the Contract Law of People's Republic of China (PRC) and the Labor Law of People's Republic of China (PRC), combined with the specific conditions of this project, and to ensure the project quality, the following agreement was reached through consultation between both parties.

First, the entry time:

Party B (responsible person) will bring the required personnel to the site.

Second, the way of contracting:

If the contractor does not package materials, it shall be guaranteed at the unit price agreed by both parties.

Third, the work content:

3- 1, all contents and changes contained in the construction drawings.

3-2, brick wall, concrete wall cleaning, spatula and water wetting, repair frame hole.

3-3, mortar mixing, measuring, vertical transportation, scaffolding construction.

3-4. Repair of door frames after maintenance, repair of water, electricity and HVAC holes, and protection of finished products.

3-5, sporadic materials piled up on the construction site and ground ash cleaning.

Four. Project contracting unit price: (The following is the price of finished products after acceptance)

Five, engineering civilization construction requirements:

According to the requirements of provincial civilized construction site construction.

Six, engineering quality requirements:

Very good.

6- 1 This project is designed according to drawings, design changes and national codes and standards. The construction of a single project shall be carried out according to the requirements of safety technical disclosure. After the acceptance, the next working procedure can be handed over. If a "quality accident" is caused by Party B, it shall be borne and handled by Party B (the labor cost and material cost for rework shall be borne by Party B).

6-2 The construction shall be carried out in accordance with the technical regulations and procedures required by the construction organization design. Don't cut corners, and don't change drawings at will. The acceptance results shall meet the evaluation criteria.

6-3 Allowable deviation range: (unit: mm)

Verticality: 2mm

Smoothness: 2mm

Founder of Yin and Yang Angle: 2mm

6-4 After the site acceptance of each working procedure is qualified, the next working procedure can be carried out.

6-5 If the test data of each subdivisional work in construction exceeds the allowable deviation, it shall be executed according to the provisions of test punishment of each subdivisional work.

Seven. Responsibilities of Party A and Party B:

1, * * * agreed to perform this contract.

2. Party A is responsible for the technical safety disclosure and material supply of the whole project and individual projects, as well as the normal operation and maintenance of large machinery (such as tower cranes and construction elevators).

3. Party A is responsible for issuing the production task list and site management rules in written form, and Party B is responsible for the implementation (personnel deployment, increase or decrease). If Party B delays or violates the regulations, it will be punished according to the regulations.

4. Party B must have a single project technical director and foreman (with work license) to lead the construction team to complete the construction task.

5. All construction personnel of Party B must abide by all rules and regulations of the site, obey the unified management of the site and unite as one. Gambling, fighting and petty theft are strictly prohibited. If it is found that each person is fined more than RMB 1 1,000, those with serious circumstances will be sent to the public security organ for handling and cleared immediately.

6. Party B shall not use child labor and idle personnel without certificates or identities, and shall not bring people who are old, weak, sick and disabled or have criminal records into the site.

7. Party B's personnel must enter the site in dressing the and be posted. All working and production personnel are under the unified management of the deputies, and their lives and production have unified arrangements.

8. Consumable materials used by Party B shall be collected by quota and managed by the site office. Fill in the Application Form for Receiving Materials and Tools, which shall be signed by the foreman or technician of each project and registered in the warehouse. A single project must be picked up in the warehouse by a special person, and the final completion will be used as the settlement basis. If it is used in excess, it will be deducted by adding% to the material.

9, do civilized construction, the construction site must be kept clean and tidy, materials neatly stacked, the construction site should be finished, expected net, site clear. Construction personnel and management personnel must be equipped with two or more teams to work in turn to ensure 24-hour uninterrupted operation.

Eight, construction safety requirements:

All personnel who enter the construction site in time must wear safety helmets, have safety experience and awareness, and must abide by various safety systems at the site. It is forbidden to wear slippers and flat shoes to work, and the shelf must be solid and reliable. This project belongs to a high-rise building, so you must fasten your seat belt when working outside the frame. Barbaric construction and illegal construction are strictly prohibited. It is forbidden to take the elevator to and from work, to rush and crowd, and to overload. Temporary electricity consumption for overtime work in the dormitory of construction personnel must be managed by on-site electricians, and it is strictly forbidden for individuals to pull wires, open machinery and use electric furnaces without permission. All mechanical teams and mechanics on site are forbidden to use drivers without permission, and must be operated by professional mechanics. The team leader of individual construction must strengthen the safety responsibility education for employees, enhance safety awareness, and report hidden dangers to the foreman of this type of work in time. All unsafe accidents such as all construction personnel of Party B failing to operate according to the specifications and safety technical disclosure when going to and from work and going out after work shall be borne by Party B, and Party A shall not be held responsible.

Nine, the construction period:

The construction period of this project is from year to year, and the construction period is days. If the project is completed on schedule, 3% of the total labor cost will be rewarded; if it is overdue, 5% of the total labor cost will be fined every day.

X. Settlement method:

After the completion of the project, the person in charge of the site, the quality inspector, the security inspector, the technician, the supervisor, and the construction unit will carry out layer-by-layer acceptance of the project according to the national acceptance evaluation standard, and the corresponding price will be applied according to the acceptance results of each layer. Relevant personnel of Party B shall go to the site office to settle accounts with the total quantity of all kinds of materials in the warehouse and the procedures for collecting various awards and fines received during the construction. The statement shall be signed by the foreman in charge, the quality inspector and the project manager and sent to the company for financial accounting payment (the contract must be brought when settling accounts).

Eleven, project quality deposit:

1. Pre-press before entering the site 10000 yuan, and return it after acceptance.

2. The contracted project has not been accepted or needs maintenance, and it needs to be detained for other reasons.

3. After the completion of the project, the warranty fee is 5% of the total labor cost, and no quality problems will be returned after the project acceptance warranty period. (The warranty period is the national legal period)

Twelve. Payment terms:

1, and pay 60% of the labor cost according to the monthly engineering quantity.

2. Pay 80% of the total labor cost upon completion of the project.

3. Pay 95% of the total labor cost after the project completion acceptance and delivery.

4. 5% of the remaining labor costs shall be paid within one year from the date of handover and acceptance.

Thirteen. Other matters:

1. Matters not covered in this contract shall be settled by both parties through consultation.

2. In case of any dispute in the implementation process, it shall be settled through consultation on the principle of friendship, equality and mutual benefit, and the local administrative organ may conduct mediation and arbitration when necessary.

3. Party B's management personnel and workers entering the construction site shall be registered and shall not be replaced at will. In case of replacement due to special reasons, Party A's consent must be obtained, and all responsibilities arising therefrom shall be borne by Party B..

4. Sporadic employment outside the main project and civilized construction on the construction site are calculated by 18 yuan/man-days.

5. Those who unintentionally damage the instrument and seriously waste materials will be compensated according to the original price, and will be financially punished.

6. Party B shall not intentionally stop work or cause losses to Party A due to price increase or other reasons, otherwise, Party A shall have the right to claim compensation, and the losses shall be deducted from the labor cost, and have the right to terminate the contract and replace the contractor. When there is a big dispute between the two parties, it shall be reported to the relevant legal department under the jurisdiction of the general contractor for judgment according to law.

7. Before obtaining the qualification of subcontractor, Party B temporarily signs in his own name, which has the same legal effect.

8. Party B shall be fully responsible for the production, living, labor, safety education, wages and labor insurance benefits of the personnel recruited to the site by the signatory himself as the beneficiary.

9. This contract is made in ten copies, with Party A holding seven copies and Party B holding three copies, which shall come into effect after being signed by both parties.

10. After the whole project is completed and the quality guarantee money is returned, this contract is invalid.

1 1. Party B must abide by the management rules of the company, and if it violates them, it will be deducted from the progress payment of the month. (Management rules are attached to the contract)

Fourteen Additional terms:

Party A: (signature and seal)

Party B: (signature and seal)

Date:

House exterior wall coating renovation contract 5 Party A:

Party B:

Party B undertakes the construction of the external wall decoration project of Building () where Party A is located, and both parties reach the following opinions through consultation:

1. Nature of the project: Party B contracts the project and materials (double contracting).

Second, the construction technology: scraping the white cement twice, sanding once, and painting the exterior wall twice (white).

Three, quality requirements: no peeling, no shedding, bright, mid-range exterior paint or above. The warranty period is three years (warranty period).

4. Project cost: RMB 10 per square meter (RMB/square meter), and the project payment is calculated according to the actual completed area.

Verb (abbreviation of verb) payment method: if the project is paid in full after acceptance, the balance will be paid in advance as quality guarantee.

Safety of intransitive verbs: operate according to the construction specifications, and Party B shall bear all safety responsibilities.

Seven, Party A's existing scaffolding, Party B can borrow the construction, and Party B is responsible for checking and strengthening the safety.

8. Time limit: the project task shall be completed within days from the date of commencement.

Nine. This agreement is made in duplicate, one for each party, and shall come into force after being signed.

Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _

Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Exterior wall coating renovation contract 6 Party A:

Party B:

According to the Construction Law of People's Republic of China (PRC) and other relevant laws and regulations, Party A and Party B follow the principles of equality, voluntariness, fairness, honesty and credibility. Party A agrees to contract the external decoration project of the office building to Party B for construction. In order to clarify the rights and obligations of both parties, the following terms and conditions are reached on relevant matters through consultation, and both parties are expected to abide by them:

1. Project content: office building exterior wall latex paint.

2. Contracting method: contracting, contracting materials, contracting quality and contracting period.

3. Project unit price: RMB one hundred and sixty-six Yuan only per square meter (16 yuan/㎡).

4. Engineering survey: Calculate the developed area of doors and windows according to the actual developed area, and deduct the area of doors and windows. External scaffolding shall be provided by Party A, and the bedding of scaffolding shall be provided by Party B. ..

Verb (abbreviation of verb) payment method: the project will be paid according to the progress. After the external wall base is processed, 25% of the project cost will be paid after pouring the bottom, 50% of the total project cost will be paid after completion, 20% of the project cost will be paid after acceptance, and the remaining 5% will be paid as warranty money one year later.

Duration of the intransitive verb contract: the construction date is days. Completed from year month day to year month day.

7. Project quality: the project is completed and accepted according to the current national standards. The quality level is not less than qualified. The materials used must meet the quality requirements of qualified products, the colors and patterns meet the design requirements, and the coating is evenly bonded and firm, without missing coating, undercoating, peeling and powder dropping. Alkali-resistant primer is used for base treatment, and the coating is consistent with other decoration materials, with clear interface and uniform color. The quality is guaranteed for five years.

Eight. Safety: Party B shall pay attention to construction safety during construction. In case of safety accidents caused by inadequate construction safety measures, Party B shall be responsible, and Party A shall not bear any legal responsibilities.

Nine. This agreement shall come into force after being signed and sealed by both parties, and shall become invalid after all the completion acceptance and settlement of the final payment. This agreement is made in duplicate, one for each party. If there are any matters not covered in this agreement, they can be settled through negotiation in a sincere and friendly way.

Party A (official seal): _ _ _ _ Party B (official seal): _ _ _ _ _

Legal representative (signature): _ _ _ _ _ Legal representative (signature): _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Exterior wall coating of house renovation contract 7 Owner: _ _ _ _ _ _ _ _ _ _ _ _.

Party A for short: _ _ _ _ _ _ _ _ _ _ _

Construction party: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

Party B for short: _ _ _ _ _ _ _ _ _ _ _

1. The owner has a two-and-a-half-story building that needs interior and exterior decoration. Through consultation, Party A and Party B have reached the following agreement. The second semi-external wall is polished with cement, the square area is 1 1 yuan, and the quality is required to be smooth.

Second, the plastering interior wall contains scraping magnetic powder at a unit price per square 39 yuan, and (the square calculation of eucalyptus board surface) five squares are calculated for each staircase. Three stairs.

3. Before Party B starts construction, Party A must prepare the materials used by Party B and shall not delay Party B's construction.

Four. Party B must ensure safety first in the construction process. In case of unsafe accidents, the responsibilities shall be borne by Party B, but not by Party A..

Five, in the construction of a part of the project, Party A will advance a part of the economy to Party B for living expenses and other expenses. After the cement of the external wall is cleaned, Party A shall pay the salary in one lump sum. After the completion of the interior wall project, it should also be paid in full.

Six, the above terms, both parties must abide by, and shall not violate, this contract shall come into force after both parties sign and seal, and shall be protected by law.

Seven. This contract is made in duplicate, one for each party.

Party A: _ _ _ _ _ _ _ _ _ _ _

Party B: _ _ _ _ _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

;