What is the format of closing the report sample?

The template format of shutdown report is as follows.

1. Project name: 220kV transformer tie line project in yuanjiacun, Lan County, Lvliang.

2. Construction unit: Taigang Group Lanxian Mining Co., Ltd.

3. Supervision unit: Shanxi Jintong Project Management Consulting Co., Ltd.

4. Construction unit: Shanxi Century Xinsheng Electric Power Co., Ltd. ..

5. Work stoppage date: 20 1x year 065438+1October 6.

6. Estimated shutdown days: 30 days.

7. Zhijintong Project Management Consulting Co., Ltd. ..

8. The tie line project of yuanjiacun 220kV substation in Lan County, Lvliang started on July, 2065 1 1. Now for the following reasons, it is required to stop construction. I hereby report it, please reply.

9. Reason for shutdown: 90% of the foundation works have been completed, so it is impossible to carry out winter construction. The erection of the iron tower has completed three foundations, and the second foundation can only be assembled after the power failure. The procedure of power failure is being handled, and the remaining tower materials have not arrived yet.