The construction scheme of the directional resettlement housing project for the protection of the old city in Xicheng District, No.7 Changyang Station, Fangshan District, strictly implements the Interim Measures for the Administration of Synchronous Delivery and Use of Houses and Municipal Public Infrastructure and Public Service Facilities in Newly-built Commercial Residential Areas in Beijing, the Implementation Plan for Comprehensive Acceptance and Handover of Municipal Public Infrastructure and Public Service Facilities in Newly-built Residential Areas in Fangshan District and related requirements. The details are as follows:

I. Overall Construction Stage

The total construction scale of this project is 461857.40m2, which will be developed and constructed in four phases. (Representation method of building number: building S*# in the south plot and building N*# in the north plot), in which:

The first phase of construction scope: east to the green belt of the community, south to Liangjing Road, and west to the planned Binhe Road; North to planning Weisi Road;

Phase II construction scope: green belt in the east, Liangjing Road in the south and planned road in the west; North to the green belt in the community;

Phase III construction scope: Yi Bei Road in the east, Liangjing Road in the south and the planned Binhe Road in the west; Plan the road to the north of the community;

Phase IV construction scope: planning Yi Bei Road in the east, planning road in the community in the south and planning Binhe Road in the west; North to planning Weisan Road;

Second, the construction content

1, Phase I construction area103219.27m2.

Construction content: S 10#, S1#, S 18#-S22# residential buildings, S 17# supporting houses, S-CK 1 underground garage.

Public service facilities: commercial services (located on the first and second floors of building S 17#, with a construction area of 2,000 square meters);

Elderly activity station (located on the ground floor of building S 17#, with a building area of 322 square meters);

Bicycle parking place (located on the first floor of each residential building with a construction area of 3,000 square meters);

Underground garage (located on the first and second floors of S-CK 1 underground, with a construction area of 12404 square meters);

Municipal public infrastructure: distribution room (located on the second floor of S-CK 1 with a construction area of 200 square meters);

Cable TV photoelectric conversion room (located on the first floor of each building, with a construction area of 60 square meters);

Thermal point (located in S-CK 1 basement with a building area of 750 square meters);

Municipal roads in this period: 3,500 square meters;

Road collection in this period: 37,500 square meters;

Green area in this period:12000m2;

Green area collected in this period: 1000 square meters.

Planned construction time: August 2065438 +0 1 to June 2065438 +03.

2. The construction area of Phase II is 92,088.75 square meters.

Construction contents: S7#, S 12#, S 13#, S 14#, S 16# residential buildings, S 15# supporting houses and S-CK2 underground garage.

Public service facilities: community health service station (located on the second floor of building S 15#, with a construction area of 386 square meters);

Property management room (located on the second floor of Building S 15#, with a construction area of 322 square meters);

Outdoor cultural and sports venues (located near the central green space, with a construction area of 100 m2);

Bicycle parking place (located on the first floor of each residential building with a construction area of 3,000 square meters);

Underground garage (located on the first and second floors underground of S-CK2, with a construction area of 28,324.18m2);

Civil air defense works (located on the first and second floors of S-CK2, with a construction area of 22 1 18 square meters);

Municipal public infrastructure: post office (located on the first and second floors of building S 15#, with a construction area of 322 square meters);

Power distribution room (located on the second floor underground of S-CK2, with a building area of 200 square meters);

Cable TV photoelectric conversion room (located on the first floor of each building, with a construction area of 50 square meters);

Municipal roads in this period: 2,000 square meters;

Collection road in this period: 0 m2;

Green area in this period:14000m2;

Green area collected in this period: 4,705 square meters.

Planned construction time: August 2065438 +0 1 to June 2065438 +03.

3. The construction area of Phase III is108085.438+08m2.

Construction content: supporting houses of S 1#, S3#, S4#, S6#, S8#, S9#, S2#, S5#, N5#, N 13#, N 14#, and municipal public infrastructure of N6#.

Public service facilities: commercial services (located on the first and second floors of S5# building, with a construction area of 2,000 square meters);

Outdoor cultural and sports venues (located near the central green space, with a construction area of 100 square meter);

Nursery home (located in S2# building, construction area 1449 m2);

Supporting schools (located in Building N 13#, with a construction area of10513m2);

Kindergarten (located in Building N 14#, with a building area of 4,582 square meters);

Vegetable market (located on the ground floor of Building N5#, with a construction area of 322 square meters);

Commercial services (located in Building N5, with a construction area of 2118m2);

Neighborhood Committee (located on the third floor of Building N5 with a building area of 322 square meters);

Community service center (located on the third floor of Building N5, with a building area of 322 square meters);

Civil air defense project (located in N5# basement with construction area of 1 100 m2);

Bicycle parking place (located on the ground floor of each residential building with a construction area of 408 1 m2);

Municipal public infrastructure: CATV photoelectric conversion room (located on the first floor of each building, with a construction area of 50 square meters);

* * * Toilet (located on the ground floor of S2# building with a construction area of 120m2, and on the ground floor of N5# building with a construction area of 41m2);

Boiler room (located in Building N6, building area1050m2);

Municipal roads in this period: 6,500 square meters;

Road collected in this period: 1 1000 square meters;

Green area in this period: 17294 square meters;

Green area collected in this period:1300m2.

Planned construction time: August 2065438 +0 1 to June 2065438 +03.

4. The construction area of Phase IV is 158463.55 m2.

Construction content: residential buildings N 1#, N3#, N4#, N7#, N8#, N 12#, supporting houses N9#, N 10#, N 15#, N2#, n/5 #.

Public service facilities: indoor recreation center (located in building N 10#, with a construction area of 3,220 square meters);

Outdoor cultural and sports venues (located near the central green space, with a construction area of 122 square meters);

Bus terminal (located in Building N9 with a building area of 483 square meters);

Bicycle parking place (located on the first floor of each residential building with a construction area of 4,842 square meters);

Underground garage (located on the first and second floors underground of North CK, with a construction area of 20981m2);

Civil air defense project (located in the first and second floors of N-CK underground, with a construction area of 9540 square meters);

Municipal public infrastructure: switching station (located in N2# building with a construction area of 338 square meters);

Power distribution room (located on the second floor underground of N-CK, with a building area of 292 square meters);

Cable TV photoelectric conversion room (located on the first floor of each building, with a construction area of 70 square meters);

Gas pressure regulating station (located in Building N 1 1#, with a construction area of16m2);

Hot spot (located in the basement of N-CK, with a building area of 500 square meters);

Closed cleaning station (located in Building N 15#, with construction area of161m2);

Municipal roads in this period: 3,500 square meters;

Road to be collected in this period: 25,000 square meters;

Green area in this period: 9,000 square meters;

Green area collected in this period: 4,380 square meters.

Planned construction time: 20110 to 20 13 10.

Third, the demolition progress

The site of this project is flat and there is no demolition.

Four. construction sequence

1, Phase I Project:

S 10#, S 1 1#, S 18-S22# residential buildings should be connected with S 17# commercial services, elderly activity stations, bicycle parking places, S-CK 1 underground garages.

Before the final residence S 10# is completed and accepted, all public service facilities (including underground buildings), municipal public infrastructure, roads and roads representing the public, road lighting, greening and greening representing the public, and temporary isolation measures from other projects in the first phase shall be completed.

Among them, temporary isolation measures are construction fences and enclosures.

The first phase of the project is completed in the greening season, and the construction unit is responsible for completing all the greening in the current area; If it is completed in the non-greening season, dust prevention measures should be taken and the measures should be covered.

2. Phase II Project:

S7#, S 12-S 14# and S 16# residential buildings should be connected with S 15# community health service station, property management building, bicycle parking place, S-CK2 underground garage, civil air defense engineering service facilities, power distribution room and heating point.

Before the final residence S 16# is completed and accepted, all public service facilities (including underground buildings), municipal public infrastructure, roads, road lighting, greening and temporary isolation measures from other projects in the second phase shall be completed.

Among them, temporary isolation measures are construction fences and enclosures.

The second phase of the project is completed in the greening season, and the construction unit is responsible for completing all the greening in the current period; If it is completed in the non-greening season, dust prevention measures should be taken and the measures should be covered.

3. Phase III Project:

S 1#, S3#, S4#, S6#, S8# and S9# houses should cooperate with S2# pension center, S5# commercial service, N 13# supporting school, N 14# kindergarten, N5# vegetable market, commercial service, neighborhood committee and so on.

Before the final residential building S 1# is completed and accepted, all public service facilities (including underground buildings), municipal public infrastructure, roads and roads representing the public, road lighting and greening, and temporary isolation measures from other projects in Phase III shall be completed.

Among them, temporary isolation measures are construction fences and enclosures.

The third phase of the project is completed in the greening season, and the construction unit is responsible for completing all the greening in the current area; If it is completed in the non-greening season, dust prevention measures should be taken and the measures should be covered.

4. The fourth phase project:

Residential buildings N 1#, N3#, N4#, N7#, N8# and N 12# should be connected with N 10# indoor recreation center, bicycle parking place, N-CK underground garage, public service facilities for civil air defense projects, N2# start-stop station and N9# bus. Closed cleaning stations, public toilets, cable TV photoelectric conversion rooms, municipal public infrastructure and roads should be handled together for project construction bidding, construction permits and completion acceptance;

Before the final acceptance of the N 1# residential building, all public service facilities (including underground buildings), municipal public infrastructure, roads and roads, road lighting, greening and greening representing the public should be completed in the Phase IV area.

Among them, temporary isolation measures are construction fences and enclosures.

The fourth phase of the project is completed in the greening season, and the construction unit is responsible for completing all greening during this period; If it is completed in the non-greening season, dust prevention measures should be taken and the measures should be covered.

Beijing Tian Heng Du Kang Real Estate Development Co., Ltd.

2011August 2