Self-evaluation of supervision work 1
With the passage of time, 20__ years passed quickly. At the end of this year, review the work of the year, evaluate the self-work, find out the shortcomings, and facilitate the future work.
In a busy and full year, with the strong support and care of the company and the project department, I made progress and worked hard.
Work for 20__ years:
A, engineering construction quality control
(1) Be familiar with the drawings, understand the design intent, and understand the main technological process and engineering characteristics of the construction process. For all incoming materials and semi-finished products, etc. Do a good job in the inspection data verification and quality inspection of raw materials to prevent materials that do not meet the quality requirements from being used in the project.
Arrive at the work station in advance for the construction of key parts, check the construction preparation, and record the whole construction process in time, completely and truly; Do a good job in daily patrol, inspection and inspection of each process of general construction.
Inform the project management department of the construction unit of the problems found in the patrol, inspection and inspection in time, urge the construction unit to implement the rectification, and review the inspection situation. Do our best to do a good job in quality control before and during the project construction supervision, and do the work dutifully.
Second, the construction safety courtesy control
In the process of work, we should give priority to safety prevention. Find hidden dangers in time and ask for timely rectification. Daily safety inspection, supervision and management should be done in the construction site. Should be regularly or irregularly on the site construction safety situation to conduct a comprehensive inspection. In view of the existing problems, timely issue a rectification notice, require the construction unit to carry out rectification, urge rectification, and re-examine in time.
Third, shortcomings in the work.
Sometimes we pay too much attention to one aspect in our work, find some problems in time and ask for rectification in time.
A brief evaluation of one year's work, my experience is that in the process of engineering construction, quality control and safety production control should be "four diligence":
1, eye care (problems should be found in advance);
2. Leg attendance (mostly on site, patrol and inspection);
3. Keep your mouth shut (speak in time when problems are found);
4. Hand clothing (make relevant records in time and issue a written rectification notice);
The work in the next 20 years will be busier and more substantial. We will perform our supervisory duties, make positive progress, obey the arrangement of the leaders, and strive to strengthen the inspection and inspection work in the new year, strengthen the control in the process, do our job better and more seriously, and think about the project wholeheartedly.
Self-evaluation of supervision work II
Looking back on the past and looking forward to the future, I have the joy of this year's harvest and the eager expectation for the future. Happily, with the care and help of leaders and colleagues, I have carefully studied and understood the corporate culture spirit of the company, guided by the company's service concept, and successfully completed my work and the tasks assigned by the leaders through my unremitting efforts. Hopefully, I deeply realize that there are still many shortcomings in the supervision work that need to be studied and improved. I will evaluate my own experience, reflect on my own shortcomings, improve my supervision business level and become a member of the company in the process of better and faster development. The evaluation of this year's supervision work is as follows:
I. Personal Annual Main Work Materials and Job Responsibility Performance Scenarios
20__, mainly participated in the on-site supervision of soft foundation treatment project in the central business district of Weifang Binhai Development Zone in the first half of the year, and mainly participated in the on-site supervision of artificial beach project in Weifang Binhai Tourism Resort in the second half of the year.
In this year's work, I obey the arrangement of the leader and earnestly perform my duties. During my work, I have never relaxed and strengthened my study of theory and practice, and have been strict with myself, serving the construction unit earnestly and enthusiastically, abiding by the requirements of the supervision contract, and performing the supervision duties in strict accordance with the supervision norms and procedures.
In the process of construction, the process control of each working procedure is carried out by means of standing by, patrolling and parallel inspection. Investigate and study the quality and safety problems existing in the site, find out the root causes of the problems, ask the construction party to take effective solutions to solve them, and follow up and supervise the construction party to implement rectification throughout the process to prevent similar problems from happening again.
For materials (high strength geogrid, geotextile, fence board, presser foot block, stepping stone, etc.). ) approach, according to the standards and design requirements to check the relevant inspection data submitted by the construction party, and check the appearance quality of the materials when entering the site. Materials whose appearance quality does not meet the requirements shall not be used in this project.
For the construction of key parts of the project, arrive at the station in advance, check the construction preparation work, and make a written record of the station in time and completely.
Acceptance of concealed works shall be carried out in strict accordance with the acceptance specifications. If the acceptance is unqualified, rectification should be carried out, and the next working procedure can only be carried out until it is qualified. Inform the project management department of the construction unit of the problems found in the inspection in the construction process orally or in writing, and report to the director in time to urge the construction unit to carry out rectification and re-inspection. Try your best to do a good job of supervision in the construction stage of the project.
Second, the experience and feelings at work
In the process of supervision work, after learning the supervision theory and understanding the development state of supervision industry at this stage, I deeply realized that as a supervisor, taking the initiative to think about the interests of the construction unit, being responsible for the quality of the project and the safety of the construction personnel is the belief and infinite strength of supervision work. Only with high professional skills, comprehensive quality and good professional ethics can we really do a good job in supervision and embody the practice principles of law-abiding, honesty, justice and fairness. Understand the importance of supervision work, establish a correct attitude towards supervision work, deal with various problems in construction with a realistic attitude, so as to effectively carry out work, actively use their own professional skills and intelligence, scientifically and fairly exercise supervision rights and obligations, cooperate with the construction unit, meet the requirements of the construction unit, and provide quality and efficient services for the owners.
Three. Future work plan and personal career development advice
As a young supervision worker, I love my job, have a good work style and hard-working spirit, and my work attitude is strictly prohibited. I like to study the causes and solutions of problems in engineering supervision, and I am keen on accumulating solutions to engineering problems.
In the future work, we should conscientiously perform our post responsibilities, strictly follow the national standards, and carry out supervision work based on design drawings. In the work, we should constantly reflect on our own shortcomings, strengthen the study of supervision business, constantly improve our own quality, do a good job in supervision, strengthen the study of management theory knowledge, handle practical problems flexibly, conscientiously complete all the work assigned by leaders, and strive to raise our professional and technical level to a new level and truly become a qualified supervisor.
Four. Opinions and suggestions on departmental companies
_, it is proposed that the company should provide targeted professional training for different employees and recruit more talents who have professional qualification certificates and can work independently.
2. It is suggested that the company organize talents with good public relations skills and set up relevant departments to deal with the socialization of supervision industry and the openness and complexity of supervision bidding.
Verb (abbreviation of verb) conclusion
The concern and support of company leaders and comfortable working conditions have given me the motivation to work hard. The warm care and cooperation of my colleagues make me feel comfortable and practical in my work, and the unique corporate culture atmosphere of the company makes me full of confidence in my work. I firmly believe that I can do better in my future work and contribute to the development of the company.
Self-evaluation of supervision work 3
I am _ _, 26 years old, majoring in construction engineering management, with the title of assistant engineer and the qualification of second-class constructor. He joined our company on, and was appointed by our company as the civil engineering supervision engineer of seven projects, such as Building 9, the Southern District of Beijing Economic and Technological Development Zone _ 17r 1 plot. Seven projects, including _ 17r 19# building in the southern new area of Beijing Economic and Technological Development Zone, are composed of three 24-storey and three 27-storey high-rise residential buildings, surrounded by large underground garages, with a total construction area of 122240㎡, and the projects have entered the stage of completion acceptance. Looking back on the work of the past year and looking forward to the new tasks and challenges that our regulatory authorities will face next year, I feel a lot. In retrospect, the first thing to thank is the concern and trust of the company leaders and the great help and support of colleagues.
Since I entered the construction site, I have always adhered to the standard of a high-quality management talent to define myself, love my job and earnestly complete all the work entrusted by the company's leaders and Party A. In my daily work, I can strictly define myself with high standards, stand ready within the scope authorized by laws and agreements, and strictly perform my post duties. I neither mingle with the construction unit nor insist on keeping a necessary distance from the construction agency. Stand in a fair position and solve some problems on the construction site independently.
In the process of supervision, I pay attention to "quality, progress, investment" and safety to control, mainly emphasizing pre-control and prevention, and nip in the bud. Combined with the inspection and acceptance of process control, on-site control and post-event control.
Quality control: review the quality assurance system and safety technical measures of the construction unit before the start of construction, timely require the construction unit to rectify the situation that does not conform to the project, supervise and inspect the implementation of the construction unit, urge the construction enterprise to improve the quality and safety management procedures and management system, and supervise its effective implementation of the 20 15 supervision evaluation model. Require construction personnel at all levels to hold relevant certificates; Check the validity of drawings, atlas, specifications and standards used by construction enterprises, and check the accuracy of measuring instruments and measuring instruments used (whether in the appraisal period); Review the materials, equipment and components entering the site. At present, the project has entered the stage of completion acceptance, and our department has formulated a weekly comprehensive quality and safety inspection system for construction units organized by the project department. The inspection mainly includes the following problems: the results of the last inspection, which problems have been rectified and which problems have not been rectified, and which problems have been found in this inspection, which are reflected in the weekly, monthly, weekly and monthly inspection records of the supervision. During the daily patrol, I notice the quality and safety hazards in time through oral notice or notice to the supervision engineer, so that the construction unit can make timely rectification. Sign the accepted sub-items and sub-projects every day, and timely summarize and file the information submitted by the construction unit to prepare for the smooth acceptance.
Time limit control: strictly supervise the construction enterprises to organize the construction according to the time limit specified in the approved schedule, urge the project department of the construction unit to prepare the schedule according to the time periods such as year, month and week, and review the guarantee measures for the implementation of the schedule submitted by them. Check the progress of the project image in time, report the progress of the project to the construction unit and analyze the reasons for the deviation! .
Investment control: carefully review the monthly, quarterly and annual engineering quantity statements of this major, so as to ensure the accuracy of the engineering quantity in the engineering quantity visa. Without acceptance or experience, those who do not meet the requirements will not be signed for approval.
At work, I cherish my reputation, adhere to honesty and self-discipline, fulfill my duties, refuse to accept illegitimate interests, put my position in order, and refuse to recognize my fellow villagers and call me brothers at work. Solve problems in work fairly and timely, regardless of time and remuneration at ordinary times, and stick to their posts on rest days and holidays.
_ _ years are coming to an end. Looking back on the supervision work in the past year, the deepest experience is that to do a good job in supervision, we must be strict and have a strong sense of responsibility. No matter how complicated the project is, as long as the supervisors can perform their duties meticulously according to the construction norms and regulations, they can fully grasp the whole project dynamics and control the whole project quality. At the same time, supervisors have high professional quality, and can prompt each working procedure and every link in advance. It's possible. In a word, my experience in one year's work is that as a supervisor, only with good conduct, concise business, good use of my own experience and authoritative test, clear purpose, rigorous style and respect for others can I get respect and recognition from others. As engineers and technicians, only by constantly improving their professional technical level and business skills, improving their communication skills and adaptability to the environment, can they better serve the construction of the project, promote the improvement of the project quality, and thus make themselves better developed. In my work, different pressures are also rare challenges and tests for me. Although there were many difficulties and twists and turns in my work over the past year, looking back, I learned a lot, learned a lot, and evaluated many experiences and lessons, which laid a solid foundation for better work in the future.
The past has passed, and the lessons of achievements and failures can only represent a kind of past experience. Future development depends on continuous efforts and creation in the future.
For myself, in my future work and life, I will constantly improve my shortcomings, evaluate my experience and lessons, constantly improve my professional and technical level and professional quality, constantly enrich myself, and make greater efforts for next year's work plan. At the same time, usually pay attention to self-charging, search online for exam information in time, strive for more professional qualifications for yourself, strive for an early postgraduate entrance examination, and let yourself have the ability to go to the next level; Strive to improve their comprehensive quality from all aspects, advance towards the goal of comprehensive management of talents, and make greater contributions to the company and themselves.
_ _ year is coming, and there is still a long way to go in the new year. I will meet the challenge with a brand-new working attitude and enter the new year with a brand-new working face. I firmly believe that with the guidance of the company leaders and the help of my colleagues, I will be able to better complete the tasks assigned to me by my superiors and make my due contribution to the development and take-off of the enterprise.
Self-evaluation of supervision work
_ _ _ _ Project officially broke ground on _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
I. Quality control
1, strictly control the quality of materials.
For the materials entering the site, the material certificate is required to be complete, and the materials can be put into use only after the supervisors witness the sampling materials and pass the inspection. Resolutely put an end to unqualified materials entering the site. For example, before the structure construction, timely urge the construction unit to send inspection for materials such as steel bars, cement, sand and gravel, and send inspection for welded joints of steel bars, and emphasize that special types of work such as welding should hold relevant certificates. For the material inspection results sampled by the construction unit without supervision witness, we declare them invalid and require re-sampling inspection;
2, from beginning to end to strengthen quality awareness, strict requirements, not resolutely rectification. One month after the start of the main project, we rectified the construction unit many times. Before pouring concrete, the construction unit is required to take out the concrete pouring scheme, organizational measures, personnel arrangement and general layout of the construction site, and make technical disclosure to ensure that 90% of the concrete is poured in place at one time. In order to avoid the phenomenon that the material can't be supplied in time in the casting process, continuous casting can't be realized. When can the second layer of concrete be poured after the rectification is in place? After nearly a week's rectification, the construction unit held several management meetings and team meetings respectively, and strengthened the mixing intensity of on-site concrete. So as to ensure the quality and progress of the project;
In painting, decoration and installation projects, we also have strict requirements, and all processes are inspected and controlled with Excellence as the standard. For those that do not conform to the design and construction specifications, we insist on asking the construction unit to handle or rework according to the design and specification requirements in written form such as supervision notice and engineering quality rectification notice, and we also encourage and support them in time. Subsequently, with the cooperation of the supervisor, the construction unit also showed a high degree of aggression; In terms of quality, we also take the initiative to be strict with ourselves.
3, emphasize the self-inspection, at the same time adhere to the tracking inspection and sampling work.
We require the construction unit to complete the "three self-inspections" of each working procedure, and then apply for inspection. The construction unit shall not carry out the construction of the next procedure, and the previous procedure has not been inspected. At the beginning of the project, although the construction unit still applied for acceptance, there were piles of problems, including some common sense problems; Sometimes inviting supervisors to accept the unfinished work of the working procedure clearly shows that they have omitted the self-inspection link. We refuse to accept this situation.
Of course, we don't forget to follow up while waiting for the inspection. Finding the problems in the construction process in time and pointing them out in time can avoid the large-scale rework of the construction unit and speed up the construction progress. For example, when binding the bottom reinforcement, we found that the supporting iron was too short, and some even lowered by 5 cm-6 cm. Therefore, we ask the construction unit to replace it in time and ask them to inform their processing plants as soon as possible to avoid further mistakes. In the process of steel binding, it is often found that the construction unit missed the distribution of corner steel bars of the pool wall and the range of column stirrups was wrong, and it was corrected in time. Sampling inspection is an important part of our project quality control. It is said to be a random inspection. In fact, we conduct a comprehensive inspection of more subprojects or processes. The point is that we have conducted several rechecks. For example, when concrete is cast, we randomly check the sand and gravel washing site, concrete slump and mixture ratio at any time to ensure the quality of concrete. Under normal circumstances, we conducted a comprehensive inspection of the steel bar binding and formwork support sub-projects after the formwork removal of beams and columns. In order to prevent the deviation caused by unexpected factors, we conducted a re-inspection, and found that the verticality deviation of a column was 3.5cm, and reworked it in time to avoid the passive situation caused by the completion of the upper structure.
After follow-up inspection and sampling inspection, we found many problems in the construction in time, and put forward suggestions to the construction unit in time to find ways to solve the problems, which also established the prestige of our supervisors and made the construction unit feel that we were not only supervising them, but also helping them.
4. Strengthen pre-control.
Strengthening pre-control can not only reduce the problems in the construction process, avoid unnecessary rework, but also speed up the project progress. As a supervisor who has designed many waterworks in the past, we are familiar with similar buildings and structures, so it is easier to do a good job in pre-control of house construction supervision. We mainly start from the following three aspects: first, before each sub-project starts, we should have a thorough understanding of the drawings, find out the problems that were not found in the joint review of drawings, and avoid the phenomenon of rework caused by rediscovery in construction; Second, before the start of each working procedure and subdivisional work, remind the construction unit of the problems that should be paid attention to, and control the key point is the size point and common faults that are prone to occur; Third, the construction unit is required to conduct technical disclosure and process disclosure before the commencement of each sub-project. For example, in the structural construction stage, the construction joints and the remaining parts of construction joints should be handled well. For the construction of long-span beam, remind the construction unit to pay attention to arching, and strengthen the vibrating and maintenance work, requiring the beam to leave no construction joints.
Second, the schedule control
Progress and time limit for a project are also important data that we control. After the construction unit comes up with the overall progress plan, we require the construction to be equipped with the overall network diagram, and take out the monthly plan and weekly plan on time. The weekly plan shall be checked and implemented at the weekly meeting, and the monthly plan shall be implemented when reviewing the monthly progress payment of the construction unit. When the weekly plan and monthly plan are not completed on schedule, please ask the construction unit to analyze the reasons first, and then come up with measures to catch up with the lagging progress. When the project reaches the necessary stage, the construction unit is required to clean up the workload and reverse the scheme. Supervisors often communicate with the person in charge of the construction unit to understand the reasons for the difficulty in completing the progress, and make suggestions and find ways for the construction unit in time. For example, in the structural construction stage, due to the large amount of steel pipes and templates, it is difficult to turn around. We report to the leaders of the construction unit in time and ask them for their support to ensure the progress of the project.
Third, investment control.
In the process of project implementation, the supervision department strictly examines the monthly progress payment submitted by each contractor and pays it in strict accordance with the measurement and payment methods agreed in the contract. Treat the design changes proposed by all parties with caution, carefully examine them, and effectively control the increase in investment. During the final accounts of the project, we responded to the bidding documents and examined them item by item, and strictly checked the accuracy and quota of the quantities and charging standards in the final accounts of the contractor.
Fourth, coordinate work.
Our main coordination work is within the project, mainly between relevant units within the project. The early stage of the project is mainly civil engineering. Later, the installation work was carried out in an all-round way, with many construction teams and coordination work. On the one hand, we emphasize that all construction units should cooperate and communicate with each other; On the other hand, grasp the progress of each unit in time, make overall plans for research and adjustment.
V. Safe and civilized production
Emphasize safe and civilized construction from beginning to end. Such as hanging safety signs and slogans on site; Safe use of electricity; Wear safety helmet and set up safe passage when entering the site; Special type of work personnel hold relevant certificates, and strictly abide by the operating procedures; On-site materials are stacked in an orderly manner, and on-site safe and civilized construction is carried out effectively.
Six, the important process and disciplines, division of engineering quality certification scheme
The important working procedures, sub-items and sub-projects of this project, from materials to structural entities, have been tested and certified by qualified testing and testing units. The specific scenario is as follows:
1. The foundation and foundation division have inspection records of the foundation trench, the main structure has statistical evaluation records of the strength of concrete test blocks and mortar test blocks, and * * * _ _ copies of the concrete compressive strength test report;
2._ _ Copies of factory certificates and inspection reports of raw materials that directly affect the quality of related projects;
3. Full water test report, roof irrigation test and witness test report _;
4. Take cover engineering acceptance record _ _ copies, ready-mixed concrete certificate _ _ _;
5. The branch project quality acceptance record _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
6. The installation project quality sampling site;
7. More than one subentry project quality acceptance record and more than one subentry project quality acceptance record are all qualified.
Seven, supervision and sampling quality on-site statistics and data summary
1. Sampling of engineering materials;
2. Civil engineering quality sampling site;
3. Inspection lot: _ _ copies, all of which are qualified;
4. On-site sampling inspection of installation engineering quality;
5. Inspection lot: _ _ copies, all of which are qualified.
Eight, review opinions on the project completion data
After reviewing the contractor's construction technical data, quality assurance data, quality inspection and evaluation data and as-built drawings, we believe that all the data are basically complete, true and complete, and meet the requirements of acceptance specifications and standards.
_ _ _ In the supervision of engineering construction, all the staff of the supervision department of this project can unite and cooperate, strictly observe discipline and work diligently, fully realize the objectives of supervision contract and good faith contract, and ensure the quality and quantity of the comprehensive business building construction project of Evergreen Garden Water Supply Pressure Transfer Station. While handing in a satisfactory answer sheet for the owner, it also fully reflects the high technical quality and ideological quality of our supervisors. Their work achievements have been fully affirmed by the owner, and they have also won a reputation and established a reputation for our supervision company.
Self-evaluation of supervision work
As time goes by, a year will soon pass. At the end of this year, review the work of the past year, calm down, evaluate the achievements and gains of your work, and find out the shortcomings for future work. It has been a great help to my work evaluation in the past year. I sincerely hope that everyone will give tips on the improper evaluation. In the past year, with the strong support and care of the leaders of the company and the project department, I earnestly adhered to the guiding ideology of pre-control, standardization, science and high quality, firmly established the service tenet of ensuring the satisfaction of every owner, and worked hard wholeheartedly. Let's talk about my work and performance in the following aspects:
I. Information management
(1) Correspondence between units shall be registered by numbers respectively, and then the receipt processing sign shall be filled in, submitted to the director for approval, and submitted to the reading clerk as instructed. And promptly supervise and handle it in time.
(2) In order to facilitate the preparation of meeting minutes, attend every meeting on time and make records. Because the summary is an incisive exposition and high generalization of the meeting materials, it is higher than the meeting minutes. This involves the conversion from oral language to technical terms. Make progress if you don't understand, and ask my colleagues for advice to make the work more perfect.
(3) Most of the data of the monthly supervision report comes from the monthly construction report. Before making the monthly report, we must study the monthly report of construction carefully and understand the details thoroughly. Only in this way can we determine whether some scenes are true or not.
Second, the quality control of engineering construction
(1) After receiving the engineering construction drawings, I will be familiar with the drawings, understand the design intent, understand the main technological process and engineering characteristics of the construction process, record the objections on the construction drawings in writing, and submit them to the chief supervision engineer at the meeting of the blue prints.the design, which will be made clear by the design.
(2) Process control of all incoming materials and semi-finished products. In addition to checking the relevant inspection data submitted by the contractor according to the standards and design requirements, I also do a good job of visual inspection of the appearance quality of the materials when they enter the site, so as to prevent the appearance quality from being inconsistent. For the construction of key parts of the project, it is necessary to arrive at the site in advance, check the construction preparations, and make written site records in a timely, complete and true manner throughout the construction process; Do a good job in daily patrol, inspection and inspection of each process of general construction. Inform the project management department of the construction unit in oral or written form of the problems found in the patrol, inspection and inspection in the construction process, report to the director in time, and urge the construction unit to implement the rectification and re-check the inspection. Do my best to control the quality of construction supervision in advance and in the process, and do my job well.
Three, safety etiquette construction control work
After studying the Law on Work Safety, I gained some experience in the course of my work, and established the view that safety prevention comes first, that is, the work should be done well first, because accidents can be prevented, but they are unpredictable, and corresponding inspection systems should be established to find hidden dangers and rectify them in time. The supervisor has an unshirkable responsibility for the safety of the construction site. In addition to daily safety inspection and supervision and management (filing and sorting of relevant data records), we should adhere to the daily safety education of the construction unit, technical post safety technical education and post safety technical disclosure inspection (including safety account and written materials), conduct a comprehensive inspection of the site construction safety status regularly or irregularly every month, and file the safety inspection record account. In view of the engineering safety control requirements put forward by the company's leaders, deepen supervision and management, issue rectification notices in time for existing problems, require the construction unit to carry out rectification, urge rectification and re-examine in time. My experience is that quality control in the process of engineering construction supervision, especially safety and civilized production control, should and must implement four due diligence systems: eye due diligence (to be able to find problems in advance); Attendance on foot (mostly on-site rotation, patrol and inspection); Keep your mouth shut (talk more about the problems found); Manual attendance (make relevant records in time and notify in writing); Only by strengthening the inspection work and strengthening the control in the process can we do the work better and more seriously. The work in 2008 was both busy and full. In order to fulfill the supervision duties, work hard, work hard, obey the leadership arrangement, never shirk, and think of the project wholeheartedly.
Five articles on self-evaluation of supervision work:
★ Model essay on self-evaluation of supervision work
★ Self-evaluation of supervision work
★ Work self-evaluation of supervision engineer
★ Model essay on supervision engineer's work self-evaluation
★ Model essay on supervision engineer's work self-evaluation
★ Self-evaluation report of supervision work
★ Model essay on self-evaluation of supervision work (2)
★ Self-evaluation of supervision work
★ Supervision engineer evaluates himself at work.
★ Model essay on supervision engineer's work self-evaluation (2)
- Related articles
- Does the recruitment interview of Shanxi institutions need a full video?
- Where is Linyi Shunda Meat Factory in Huangdao District?
- Teachers of Chuzhou TV University
- Embroidery machines are always misplaced! Help urgently!
- Does the game need world view support?
- How about Yuhuan County Chenyu Yongfeng Mechanical Valve Factory?
- What is the process of applying for the equivalent academic qualification of administrative management major in Nankai University in 217?
- China Life R&D Center Property & Casualty Insurance
- Which eye hospital in Foshan is the best?
- How about Shaanxi Jia Lian General Electric Co., Ltd.